Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

EIA Compliance: New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works

MATTM - Logo stella

21/11/2019

The EIA compliance determination (DEC 370 of 21/11/2019) related to the project "New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works" has been issued with a "ottemperata" outcome.

Go to the project

Download the determination