Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

EIA Compliance: Caorso nuclear power plant - Updating of the radioactive waste management methods and related in situ temporary storage

481_Centrale di Caorso

26/03/2015

The EIA compliance determination (DVA-DEC-2015-0000043 of 26 March 2015) on the prescriptions 1.a.1, 1.a.2, 1.a.3 and  2.a of the EIA Screening determination no.18706 of 6 August 2013 related to Caorso nuclear power plant – Updating of the radioactive waste management  methods and related in situ temporary storage has been issued with favourable outcome.

Go to the project

Download the determination