Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

EIA Compliance: Accelerated decommissioning process for the unconditional release of the site – Trino (Vercelli) nuclear power plant

610_trino_vercellese

17/03/2015

The EIA compliance determination (DVA-DEC-2015-0000025 of 17 March 2015) on the prescription no. 9 of the EIA Decision no. 1733 of 24 December 2008 related to the project Accelerated decommissioning process for the unconditional release of the site - Trino nuclear power plant has been issued with favourable outcome.

Go to the project

Download the determination