Environmental Impact Assessment: New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works

MATTM - Logo stella

04/08/2022

The EIA decision (D.M. DEC-2022-0000171 of 04/08/2022) related to the project "New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works" has been issued with a "ottemperata" outcome.

Go to the project

Download decision