EIA: Construction of the offshore LNG regasification plant of 4 billion cubic meters/year capacity located in Falconara Marittima

249_GNL_offshore_Falconara_marittima_rev1

11/08/2015

The EIA decision D.M. 181 of 11 August 2015 has extended to 12 August 2019 the validity of the EIA Decision n. 375 of 22 July 2010 related to the offshore LNG regasification plant of 4 billion cubic meters/year capacity located in Falconara Marittima.