Procedure Code (ID_VIP/ID_MATTM): |
3053 |
Date of application submission: |
07/07/2015 |
Publication date of the notice in newspapers: |
06/07/2015 |
Technical assessment starting date: |
04/08/2015 |
Republication date of the notice in newspapers: |
29/07/2015 |
Deadline of submission of Public Comments on the republished project: |
27/09/2015 |
Date of request for integrations for the republished project: |
11/05/2016 |
Date of integrations related to the republished project receipt: |
26/07/2016 |
Second Republication date: |
25/07/2016 |
Deadline of submission of Public Comments - Second republication: |
27/09/2016 |
Second republication subject
: |
Integrazioni del 26/07/2016 |
Date of the Opinion of the National Technical Commission on usage Plan: |
21/04/2017 |
Opinion number of the National Technical Commission on usage Plan: |
2374 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato con prescrizioni |
Usage Plan Determination date: |
22/06/2017 |
Determination number on usage Plan: |
DVA-DEC-2017-0000198 |
Usage Plan Determination outcome: |
Approvato con prescrizioni |
Date of the Opinion of the National Technical Commission : |
09/06/2017 |
National Technical Commission Opinion number: |
2416 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
28/03/2023 |
EIA Decree number: |
DM_2023-0000156 |
EIA Decree outcome: |
positivo |
Notification date: |
29/03/2023 |
Notification Reference number: |
MASE-2023-0048216 |
Notes: |
Con nota del 30/05/2016 (prot. DVA-2016-0014565) è stata concessa una proroga di 45 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |