Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Modifications to the IGCC plant - Changing the CCPP natural gas combined cycle of the industrial site of Falconara Marittima (AN)


General information

Work: Thermal power plant of Falconara Marittima (Ancona)

Project: Modifications to the IGCC plant - Changing the CCPP natural gas combined cycle of the industrial site of Falconara Marittima (AN)

Description: Changes to the IGCC plant to ensure the provision of necessary steam to the Refinery units and the electrical energy for the needs of the site. Main planned interventions: replacement of some internal parts of the combined cycle gas turbine, installation of a system to reduce the CO in the recovery boiler, the construction of a new section of pipe and changes to the energy distribution system inside the site

Developer: Api Energia S.p.A.

Project type: Thermal power plant

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Marche

Provinces: Ancona

Municipalities: Falconara Marittima

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
EIA Compliance 2673 24/03/2014 Concluded Procedure details Documents
EIA Compliance 2745 19/02/2014 Concluded Procedure details Documents
EIA Screening 1993 24/07/2012 Concluded Procedure details Documents