Requalification of the existing Chiomonte-Susa hydroelectric plant


General information

Work: Hydroelectric plant of Chiomonte-Susa

Project: Requalification of the existing Chiomonte-Susa hydroelectric plant

Description: Redevelopment of the Chiomonte-Susa hydroelectric plant through the renovation of existing facilities and the construction of several new works aimed at the functional optimization of the facilities to maintain the sustainable use of water for hydroelectric purposes downstream the Pont Ventoux barrage.

Developer: IREN Energia S.p.A.

Project type: Hydroelectric facility

Deadline for submission of comments: 02/09/2012 mail

Territories and marine areas

Map

Regions: Piemonte

Provinces: Torino

Municipalities: Susa, Giaglione, Chiomonte, Gravere

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
EIA Screening 1989 19/07/2012 Concluded Procedure details Documents