EIA Compliance (Strategic works Law 443/2001) |
10267 |
10/08/2023 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10267 |
Subject
: |
Piattaforma d'altura al Porto di Venezia - Terminal container di Montesyndial |
Date of application submission: |
10/08/2023 |
Technical assessment starting date: |
18/09/2023 |
Date of the Opinion of the National Technical Commission : |
10/11/2023 |
National Technical Commission Opinion number: |
891 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
04/12/2023 |
Determination number: |
MASE_VA_DEC_2023-0000624 |
Determination outcome: |
Parzialmente ottemperata |
Notification date: |
07/12/2023 |
Notification Reference number: |
MASE_2023-0201005 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
8375 |
22/04/2022 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8375 |
Subject
: |
Piattaforma d'altura al Porto di Venezia - Terminal container di Montesyndial" di cui al provvedimento di VIA n. 1320/2013. Aggiornamento giudizio di compatibilità ambientale |
Date of application submission: |
22/04/2022 |
Date of request for documents perfection : |
19/05/2022 |
Date of perfection proceedings documents receipt: |
05/10/2022 |
Date of request for integrations: |
22/12/2022 |
Date of integrations receipt: |
16/03/2023 |
Data comunicazione avvio nuova consultazione pubblica: |
17/03/2023 |
Deadline of submission of Public Comments on the republished project: |
16/04/2023 |
Communication date of the outcome to the developer: |
24/05/2023 |
Protocol of outcome communication to the developer: |
MASE_2023-0084066 |
Outcome: |
Emanato positivo con/senza prescrizioni |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
1909 |
10/05/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1909 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
10/05/2012 |
Publication date of the notice in newspapers: |
01/09/2012 |
Deadline of submission of Public Comments: |
31/10/2012 |
Technical assessment starting date: |
15/10/2012 |
Date of integrations receipt: |
05/10/2012 |
Date of second request for integrations : |
26/02/2013 |
Date of integrations second receipt: |
12/06/2013 |
Republication date of the notice in newspapers: |
27/05/2013 |
Deadline of submission of Public Comments on the republished project: |
12/07/2013 |
Republication subject
: |
Comunicazione di deposito della documentazione in risposta alle integrazioni richieste dalla Commissione Tecnica di Verifica dell'Impatto Ambientale |
Date of the Opinion of the National Technical Commission : |
02/08/2013 |
National Technical Commission Opinion number: |
1320 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
30/08/2013 |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
1408 |
26/10/2004 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1408 |
Date of application submission: |
26/10/2004 |
Date of the EIA Decree: |
19/10/2007 |
EIA Decree number: |
DSA-DEC-2007_0000799 |
EIA Decree outcome: |
Interlocutorio negativo |
Stage of the Procedure: |
Concluded |