Offshore LNG regasification Terminal of Falconara Marittima - Project for the optimization of the 32" pipe and power and control cable landing
General information
Work: Off-shore LNG regasification Terminal of Falconara Marittima
Project: Offshore LNG regasification Terminal of Falconara Marittima - Project for the optimization of the 32" pipe and power and control cable landing
Description: Offshore LNG regasification Terminal of Falconara Marittima - Project for the optimization of the 32" pipe and power and control cable landing as an alternative to the solution authorized, by trenchless techniques, respectively through micro tunnelling at the artificial reef crossing, and horizontal directional drilling.
Developer: api nova energia
Project type: Marine terminals
Deadline for submission of comments: 07/12/2012
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Offshore LNG regasification Terminal of Falconara Marittima with a capacity of 4 billion cubic meters per year |
api nova energia |
Environmental Impact Assessment |
Info Project and procedures
|
documents
|
Terminale Offshore di rigassificazione GNL di Falconara Marittima |
api nova energia |
EIA Screening |
Info Project and procedures
|
documents
|
Territories and marine areas
Map
Regions: Marche
Provinces: Ancona
Municipalities: Falconara Marittima
Marine areas: Mar Adriatico Centrale
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
EIA Screening |
|
2081 |
22/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2081 |
Date of application submission: |
22/10/2012 |
Publication date of the notice in the Italian Republic Official Journal : |
23/10/2012 |
Deadline of submission of Public Comments: |
07/12/2012 |
Technical assessment starting date: |
31/10/2012 |
Date of the Opinion of the National Technical Commission : |
22/03/2013 |
National Technical Commission Opinion number: |
1190 |
National Technical Commission Opinion outcome: |
Escluso dalla VIA con prescrizioni |
Determination date: |
02/05/2013 |
Determination number: |
DVA-2013_10045 |
Determination outcome: |
Escluso dalla VIA con prescrizioni |
Stage of the Procedure: |
Concluded |