New 150kV double circuit power line Troia electrical substation - Roseto/Alberona electrical substation
General information
Work: 150 kV double circuit power line Troia electrical substation - Roseto/Alberona electrical substation
Project: New 150kV double circuit power line Troia electrical substation - Roseto/Alberona electrical substation
Description: The project involves the construction of a new 150 kV double circuit power line connecting Troia electrical substation to the existing 150 kV power line "Roseto-Alberona" and to the electrical substations of Roseto and Alberona. The overall length of the power line is about 14.9 km. The project allows to increase the reliability and continuity of the transmission system against the growing production of electricity from renewable sources in the Province of Foggia.
Developer: Terna Rete Elettrica Nazionale S.p.A.
Project type: Electrical power lines
Deadline for submission of comments: 18/07/2015
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Progetto collegamento 150 kV "SE Troia - SE Alberona" |
Terna Rete Italia S.p.A. |
Environmental Impact Assessment |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Puglia
Provinces: Foggia
Municipalities: Alberona, Biccari, Troia, Castelluccio Valmaggiore, Roseto Valfortore
Marine areas: None
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
|
2412 |
21/06/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2412 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
21/06/2013 |
Publication date of the notice in newspapers: |
18/06/2013 |
Deadline of submission of Public Comments: |
20/08/2013 |
Technical assessment starting date: |
16/09/2013 |
Republication date of the notice in newspapers: |
20/05/2014 |
Deadline of submission of Public Comments on the republished project: |
19/07/2014 |
Republication subject
: |
Relazione sugli effetti cumulativi sull'ambiente |
Date of integrations related to the republished project receipt: |
15/05/2014 |
Date of application for integrations related to the republished project second request: |
13/10/2014 |
Date of integrations related to the republished project second receipt : |
07/05/2015 |
Second Republication date: |
19/05/2015 |
Deadline of submission of Public Comments - Second republication: |
18/07/2015 |
Second republication subject
: |
Documentazione integrativa |
Date of the Opinion of the National Technical Commission : |
15/07/2016 |
National Technical Commission Opinion number: |
2129 |
National Technical Commission Opinion outcome: |
Negativo |
Date of the EIA Decree: |
07/02/2017 |
EIA Decree number: |
DVA-2017-00002726 |
EIA Decree outcome: |
Archiviato |
Notes: |
Con nota del 03/03/2015 (prot. DVA-2015-0005892) è stata concessa una ulteriore proroga di 60 giorni. Con nota del 14/01/2015 (prot. DVA-2015-0000966) è stata concessa una ulteriore proroga di 45 giorni per la consegna delle integrazioni. Con nota del 21/11/2014 (prot. DVA-2014-0038514) è stata concessa una proroga di 45 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |