Geothermal Pilot Plant named Castel Giorgio in the Province of Terni, in the municipality of Castel Giorgio (TR)


General information

Work: Geothermal pilot plant Castel Giorgio

Project: Geothermal Pilot Plant named Castel Giorgio in the Province of Terni, in the municipality of Castel Giorgio (TR)

Description: The geothermal pilot plant of Castel Giorgio provides for the use of the thermal energy from the geothermal field of Torre Alfina consisting of 5 production wells of hot water located in 3 pitches (CG1, CG2, CG3), a piping system carrying hot water from the wells to the ORC plant for the production of electricity by recovering heat from the hot geothermal water, 4 injection wells of geothermal water located in a single pitch (CG14).

Developer: ITW & LKW Geotermia Italia S.p.A.

Project type: Geothermal power plants

Territories and marine areas

Map

Regions: Umbria

Provinces: Terni

Municipalities: Castel Giorgio

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
EIA Compliance 12817 08/07/2024 Administrative control Procedure details Documents
EIA Compliance 11287 02/04/2024 Concluded Procedure details Documents
EIA Compliance 10786 21/12/2023 Concluded Procedure details Documents
EIA Compliance 10695 01/12/2023 Concluded Procedure details Documents
EIA Compliance 5442 13/07/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5376 17/06/2020 Concluded Procedure details Documents
EIA Compliance 5377 17/06/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5287 18/05/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5289 18/05/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5290 18/05/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5291 18/05/2020 Concluded Procedure details Documents
EIA Compliance 5288 15/05/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 5279 11/05/2020 Concluded Procedure details Documents
EIA Compliance 5278 11/05/2020 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 3547 03/02/2017 Concluded Procedure details Documents
EIA Compliance 3441 08/09/2016 Concluded Procedure details Documents
EIA Compliance 3181 13/11/2015 Concluded Procedure details Documents
EIA Compliance 3183 13/11/2015 Concluded Procedure details Documents
Environmental Impact Assessment 2557 04/10/2013 Concluded Procedure details Documents