Plant for the production and storage of methyl esters (biodiesel) to Monopoli - Increasing production capacity of the existing plant producing methyl ester from vegetable oils, new section for distillation of glycerin and new section for the production of technical esterified oils
General information
Work: Plant for the production and storage of methyl esters (biodiesel) to Monopoli (BA)
Project: Plant for the production and storage of methyl esters (biodiesel) to Monopoli - Increasing production capacity of the existing plant producing methyl ester from vegetable oils, new section for distillation of glycerin and new section for the production of technical esterified oils
Description: The project involves the expansion of the potential processing of methyl esters from vegetable oil up 360,000 t /y, the construction of a section for the distillation of the glycerine with a production capacity of about 100 t / day and a simple esterification section for the production of technical esterified oils with a capacity of about 100 t / day in the plant for the production and storage of methyl esters (biodiesel) in Monopoli
Developer: Ital Bi Oil S.r.l.
Project type: Integrated chemical plants
Related website: Procedura integrata VIA-AIA: documentazione AIA
Deadline for submission of comments: 09/11/2014
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Progetto di inserimento di una nuova linea per il trattamento rifiuti a base di olii vegetali dell'impianto Ital Bi Oil S.r.l ubicato in località contrada Baione nel comune di Monopoli (BA). |
Ital Bi Oil S.r.l. |
EIA Compliance (PNIEC-PNRR) |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Puglia
Provinces: Bari
Municipalities: Monopoli
Marine areas: None
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
|
2840 |
10/09/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2840 |
EIA-IPPC Coordinated Procedure : |
Sì |
Date of application submission: |
10/09/2014 |
Publication date of the notice in newspapers: |
05/09/2014 |
Deadline of submission of Public Comments: |
09/11/2014 |
Technical assessment starting date: |
12/09/2014 |
Date of request for integrations: |
15/04/2015 |
Date of integrations receipt: |
06/08/2015 |
Date of integrations second receipt: |
05/04/2016 |
Date of the Opinion of the National Technical Commission : |
15/04/2016 |
National Technical Commission Opinion number: |
2035 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
13/09/2016 |
EIA Decree number: |
DM-0000245 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notes: |
Con nota del 03/06/2015 (prot. DVA-2015-0014633) è stata concessa una proroga di 60 giorni, a partire dal 01/06/2015, per la consegna delle integrazioni |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |