Work: Impianto idroelettrico "Budriesse"
Project: Hydroelectric power plant "Budriesse"
Description: The project involves the construction of the hydroelectric power plant with nominal power of about 2.550 kW on the river Adda in the municipality of Castelnuovo Bocca d'Adda (LO).
Developer: VIS S.r.l.
Project type: Hydroelectric facility
Deadline for submission of comments: 07/09/2015 mail
Regions: Lombardia
Provinces: Cremona, Lodi
Municipalities: Castelnuovo Bocca d'Adda, Maccastorna, Crotta d'Adda
Marine areas: None
Procedure | Procedure Code | Starting date | Stage of the procedure | ||
---|---|---|---|---|---|
Environmental Impact Assessment | 3046 | 25/06/2015 | Concluded | Procedure details | Documents |