EIA Compliance |
3777 |
25/10/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3777 |
Subject
: |
Prescrizione A.5 del Decreto VIA n. 218 del 07/08/2017 |
Date of application submission: |
25/10/2017 |
Technical assessment starting date: |
31/10/2017 |
Date of the Opinion of the National Technical Commission : |
12/12/2017 |
National Technical Commission Opinion number: |
2574 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
18/12/2017 |
Determination number: |
DVA-DEC-2017-0000426 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carlotta Angelini - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3776 |
25/10/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3776 |
Subject
: |
Prescrizione A.1 del Decreto VIA n. 218 del 07/08/2017 |
Date of application submission: |
25/10/2017 |
Technical assessment starting date: |
30/10/2017 |
Date of the Opinion of the National Technical Commission : |
16/02/2018 |
National Technical Commission Opinion number: |
2658 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
02/03/2018 |
Determination number: |
DVA-DEC-2018-0000103 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carlotta Angelini - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
3398 |
14/07/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3398 |
EIA-AA integrated Procedure : |
Sì |
EIA-IPPC Coordinated Procedure : |
Sì |
Subject
: |
Seconda fase - G2 project - step 2 |
Date of application submission: |
14/07/2016 |
Publication date of the notice in newspapers: |
08/07/2016 |
Deadline of submission of Public Comments: |
08/10/2016 |
Technical assessment starting date: |
15/09/2016 |
Date of the Opinion of the National Technical Commission : |
21/04/2017 |
National Technical Commission Opinion number: |
2370 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
07/08/2017 |
EIA Decree number: |
DM-0000218 |
EIA Decree outcome: |
Positivo con prescrizioni |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Screening |
3094 |
06/08/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3094 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
06/08/2015 |
Publication date of the notice: |
11/08/2015 |
Deadline of submission of Public Comments: |
25/09/2015 |
Technical assessment starting date: |
12/08/2015 |
Date of request for integrations: |
02/11/2015 |
Date of integrations receipt: |
01/12/2015 |
Date of the Opinion of the National Technical Commission : |
11/03/2016 |
National Technical Commission Opinion number: |
2022 |
National Technical Commission Opinion outcome: |
Escluso dalla VIA con prescrizioni |
Determination date: |
17/03/2016 |
Determination number: |
DVA-DEC-2016-0000090 |
Determination outcome: |
Escluso dalla VIA con prescrizioni |
Notes: |
Il Progetto preliminare non è stato pubblicato per motivi di segreto industriale. |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225074 - va-5@mite.gov.it |