Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Energetic enhancement plant of secondary solid fuel in the thermal power plant of San Filippo del Mela (ME)


General information

Work: San Filippo del Mela thermal power plant

Project: Energetic enhancement plant of secondary solid fuel in the thermal power plant of San Filippo del Mela (ME)

Description: The project involves the installation of 2 boilers (200 MWt) fuelled with secondary solid fuel, the commissioning of the thermoelectric units SF1 and SF2 and the shutdown of the SF5 and SF6 units.

Developer: A2A Energiefuture S.p.A.

Project type: Thermal power plant

Deadline for submission of comments: 10/12/2016 mail

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Sicilia

Provinces: Messina

Municipalities: San Filippo del Mela

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 3127 18/09/2015 Concluded Procedure details Documents