Reconstruction of an existing river dam for irrigation, with mobile barrier for hydroelectric use and construction of a hydroelectric power plant in the municipalities of Barbaresco and Castagnito


General information

Work: Hydroelectric power plant in the municipalities of Barbaresco and Castagnito

Project: Reconstruction of an existing river dam for irrigation, with mobile barrier for hydroelectric use and construction of a hydroelectric power plant in the municipalities of Barbaresco and Castagnito

Description: The project involves the reconstruction of an existing river dam for irrigation with a mobile barrier above the fixed dam and the construction of a hydroelectric power plant.

Developer: TANARO POWER S.p.A.

Project type: Hydroelectric facility

Deadline for submission of comments: 23/11/2015 mail

Territories and marine areas

Map

Regions: Piemonte

Provinces: Cuneo

Municipalities: Castagnito, Barbaresco

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 3131 24/08/2015 Concluded Procedure details Documents