EIA Compliance |
|
5593 |
14/10/2020 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5593 |
Subject
: |
Razionalizzazione rete elettrica 220kV città di Torino - cavo interrato a 220kV del nuovo collegamento T.213 "Pianezza-Grugliasco" e dei nuovi tratti delle linee aeree a 220kV in ingresso alla S.E. Pianezza T.216 "Rosone-Pianezza" e T.231 "Piossasco-Pianezza" nei comuni di Pianezza, Rivoli, Collegno e San Gillio nella Città Metropolitana di Torino - Piano di Utilizzo Terre (PdU): Prescrizioni nn. 1 e 2 |
Date of application submission: |
14/10/2020 |
Technical assessment starting date: |
30/10/2020 |
Date of notification to the developer of the procedure outcomes: |
25/06/2021 |
Date of the Opinion of the National Technical Commission : |
28/05/2021 |
National Technical Commission Opinion number: |
264 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
22/06/2021 |
Determination number: |
DEC_2021-0000209 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
MATTM-2021-0069200 |
Outcome: |
Ottemperata |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Screening |
|
3318 |
29/03/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3318 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
29/03/2016 |
Publication date of the notice: |
31/03/2016 |
Deadline of submission of Public Comments: |
16/05/2016 |
Technical assessment starting date: |
04/04/2016 |
Date of request for integrations: |
16/06/2016 |
Date of integrations receipt: |
13/09/2016 |
Republication date of the notice: |
14/09/2016 |
Deadline of submission of Public Comments on the republished project: |
29/10/2016 |
Republication subject
: |
Documentazione integrativa |
Date of request for integrations for the republished project: |
28/10/2016 |
Date of integrations related to the republished project receipt: |
06/03/2017 |
Date of the Opinion of the National Technical Commission on usage Plan: |
06/10/2017 |
Opinion number of the National Technical Commission on usage Plan: |
DVA-DEC-2017-0000291 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato con prescrizioni |
Usage Plan Determination date: |
17/10/2017 |
Determination number on usage Plan: |
DVA-DEC-2017-0000291 |
Usage Plan Determination outcome: |
Approvato con prescrizioni |
Date of the Opinion of the National Technical Commission : |
27/10/2017 |
National Technical Commission Opinion number: |
2535 |
National Technical Commission Opinion outcome: |
Escluso dalla VIA con prescrizioni |
Determination date: |
15/11/2017 |
Determination number: |
DVA-DEC-2017-0000347 |
Determination outcome: |
Escluso dalla VIA con prescrizioni |
Notes: |
Con nota del 12/07/2016 (prot. DVA-2016-0018408) è stata concessa una proroga di 60 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |