Construction of a dock, in the locality of Pentimele in Reggio Calabria, for the mooring of the ferry to the road transport of cars and heavy vehicles for the maritime link Reggio Calabria-Messina
General information
Work: Port of Reggio Calabria
Project: Construction of a dock, in the locality of Pentimele in Reggio Calabria, for the mooring of the ferry to the road transport of cars and heavy vehicles for the maritime link Reggio Calabria-Messina
Description: The project involves the construction of 2 docks for the mooring of Ro-Ro ferries from the Reggio Calabria to Tremestieri in the northern square of the Reggio Calabria port.
Developer: Caronte&Tourist S.p.A.
Project type: Ports
Deadline for submission of comments: 24/11/2017
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Port of Reggio Calabria - Construction of docking area for maritime services Reggio Calabria-Messina in the northern area of the port |
Caronte&Tourist S.p.A. |
EIA Screening |
Info Project and procedures
|
documents
|
Port of Reggio Calabria - Construction of a dock, in the locality of Pentimele, for the mooring of the ferry to the road transport of cars and heavy vehicles for the maritime link Reggio Calabria-Messina |
Diano S.p.A. |
EIA Screening |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Calabria
Provinces: Reggio Calabria
Municipalities: Reggio Calabria
Marine areas: Mar Ionio Meridionale
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
|
3425 |
01/09/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3425 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
01/09/2016 |
Publication date of the notice in newspapers: |
27/09/2016 |
Deadline of submission of Public Comments: |
02/12/2016 |
Technical assessment starting date: |
04/10/2016 |
Date of request for integrations: |
02/02/2017 |
Date of integrations receipt: |
11/07/2017 |
Date of notification to the developer of the procedure outcomes: |
25/10/2019 |
Republication date of the notice in newspapers: |
25/08/2017 |
Deadline of submission of Public Comments on the republished project: |
24/11/2017 |
Republication subject
: |
Documentazione integrativa |
Date of the EIA Decree: |
22/10/2019 |
EIA Decree number: |
DM 310 |
EIA Decree outcome: |
Positivo |
Notification Reference number: |
DVA/2019/28104 |
Outcome: |
Positivo |
Notes: |
Con nota del 13/06/2017 (prot. DVA-2017-0013838) è stata concessa una proroga di 15 giorni per la consegna delle integrazioni. Con nota del 15/03/2017 (prot. DVA-2017-0006243) è stata concessa una proroga di 90 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |