Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

New 132 kV "Franchini acciai" electrical substation and 132 kV single circuit power line for the connection to the existing electrical substation of Brandico


General information

Work: 132 kV power line for the connection of "Franchini acciai" substation to substation of Brandico

Project: New 132 kV "Franchini acciai" electrical substation and 132 kV single circuit power line for the connection to the existing electrical substation of Brandico

Description: The project involves the construction of the 132 kV overhead single circuit power line to connect the new Franchini Acciai electrical station to the existing electrical station of Brandico.

Developer: e-distribuzione S.p.A.

Project type: Electrical power lines

Deadline for submission of comments: 17/05/2018 mail

Territories and marine areas

Map

Regions: Lombardia

Provinces: Brescia

Municipalities: Brandico, Mairano

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
EIA Screening 3702 05/09/2017 Concluded Procedure details Documents