Construction of the Greve in Chianti thermal power plant with a total capacity of 148 MWt


General information

Work: Thermal power plant of Greve in Chianti

Project: Construction of the Greve in Chianti thermal power plant with a total capacity of 148 MWt

Description: The project involves the installation of a 73,6 MW thermal power plant consisting of 4 endothermic engines in the municipality of Greve in Chianti.

Developer: Metaenergiaproduzione S.r.l.

Project type: Thermal power plant

Deadline for submission of comments: 23/02/2018 mail

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Toscana

Provinces: Firenze

Municipalities: Greve in Chianti

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
EIA Screening 3871 27/12/2017 Concluded Procedure details Documents