EIA Compliance |
|
12763 |
06/06/2024 |
Administrative control |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
12763 |
Subject
: |
Parco eolico Cerignola Veneta NORD nel territorio comunale di Cerignola (FG) della potenza complessiva pari a 50,4 MW - Prescrizione: 2 |
Date of application submission: |
06/06/2024 |
Date of request for documents perfection : |
06/08/2024 |
Date of perfection proceedings documents receipt: |
13/08/2024 |
Responsible of the procedure: |
Maria Ciuffreda - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Administrative control |
EIA Compliance |
|
12765 |
03/06/2024 |
Administrative control |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
12765 |
Subject
: |
Parco eolico Cerignola Veneta NORD nel territorio comunale di Cerignola (FG) della potenza complessiva pari a 50,4 MW - Prescrizione: 4 |
Date of application submission: |
03/06/2024 |
Date of request for documents perfection : |
06/08/2024 |
Date of perfection proceedings documents receipt: |
13/08/2024 |
Stage of the Procedure: |
Administrative control |
EIA Compliance |
|
12764 |
03/06/2024 |
Administrative control |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
12764 |
Subject
: |
Parco eolico Cerignola Veneta NORD nel territorio comunale di Cerignola (FG) della potenza complessiva pari a 50,4 MW - Prescrizione: 3 |
Date of application submission: |
03/06/2024 |
Date of request for documents perfection : |
06/08/2024 |
Date of perfection proceedings documents receipt: |
13/08/2024 |
Stage of the Procedure: |
Administrative control |
Environmental Impact Assessment |
|
4047 |
19/04/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4047 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
19/04/2018 |
Data avvio consultazione pubblica: |
30/05/2018 |
Deadline of submission of Public Comments: |
29/07/2018 |
Technical assessment starting date: |
30/05/2018 |
Date of request for integrations: |
26/11/2018 |
Date of integrations receipt: |
27/02/2019 |
Data comunicazione avvio nuova consultazione pubblica: |
07/03/2019 |
Deadline of submission of Public Comments on the republished project: |
06/04/2019 |
Date of the Opinion of the National Technical Commission : |
17/04/2020 |
National Technical Commission Opinion number: |
3299 |
National Technical Commission Opinion outcome: |
Positivo |
Ministry of Cultural Heritage and Tourism Opinion date: |
10/08/2020 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
MATTM64562 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Negativo |
Date of the EIA Decree: |
24/01/2022 |
EIA Decree number: |
DM_2022-0000062 |
EIA Decree outcome: |
Positivo con prescrizioni/raccomandazioni |
Notification date: |
31/01/2022 |
Notification Reference number: |
MiTE_2022-0011146 |
Stage of the Procedure: |
Concluded |