IPPC permit for non substantial changes |
|
75/16663 |
17/07/2024 |
IPPC Technical Committee's assessment |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/16663 |
Reference of previous authorization's Act: |
DM 513 del 12/12/2022 |
Application submission date: |
17/07/2024 |
Ministry Protocol Application submission: |
prot. MASE/132874 |
Ministry Protocol date of application submission: |
17/07/2024 |
Subject: |
Sostituzione filtropressa (ITAR - Impianto Trattamento Acque Reflue) e Variazioni delle aree di deposito temporaneo rifiuti |
Procedure starting date : |
23/07/2024 |
Launch of public consultation: |
23/07/2024 |
Deadline of submission of Public Comments on IPPC permit: |
22/08/2024 |
Stage of the Procedure: |
IPPC Technical Committee's assessment |
Reconsideration of compliance to permit conditions |
|
75/15617 |
22/12/2023 |
IPPC Technical Committee's assessment |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/15617 |
Reference of previous authorization's Act: |
DM 513 del 12/12/2022 |
Application submission date: |
22/12/2023 |
Ministry Protocol Application submission: |
prot. MASE/211653 |
Ministry Protocol date of application submission: |
22/12/2023 |
Subject: |
Dismissione e ripristini dei luoghi |
Procedure starting date : |
19/01/2024 |
Launch of public consultation: |
19/01/2024 |
Deadline of submission of Public Comments on IPPC permit: |
18/02/2024 |
Stage of the Procedure: |
IPPC Technical Committee's assessment |
IPPC permit for substantial changes |
|
75/11079 |
05/11/2020 |
on-going procedure |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/11079 |
Reference of previous authorization's Act: |
D.M. 121/2011 |
Application submission date: |
05/11/2020 |
Ministry Protocol Application submission: |
Prot. MATTM_91521 |
Ministry Protocol date of application submission: |
09/11/2020 |
Subject: |
stralcio della prescrizione di cui al paragrafo 5 del Parere istruttorio conclusivo del 10 marzo 2015 circa il piano di dismissione e messa in sicurezza dei gruppi di generazione elettrica turbogas PF3-PF4 presentato in attuazione della disposizione di cui all'art. 1,c.5, del decreto AIA dec. N. 121 |
Procedure starting date : |
20/11/2020 |
Launch of public consultation: |
20/11/2020 |
Deadline of submission of Public Comments on IPPC permit: |
20/12/2020 |
Stage of the Procedure: |
on-going procedure |
IPPC permit for non substantial changes |
|
75/10653 |
31/01/2020 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/10653 |
Reference of previous authorization's Act: |
DVA-DEC-2011-0000121 del 28/03/2011 |
Application submission date: |
31/01/2020 |
Ministry Protocol Application submission: |
MATT-2020-10875 |
Ministry Protocol date of application submission: |
17/02/2020 |
Subject: |
Modifica non sostanziale |
Procedure starting date : |
12/03/2020 |
Launch of public consultation: |
29/04/2020 |
Decision Number: |
PIC nota prot. n. CIPPC/1154 del 24/8/22 |
Decision Date: |
24/08/2022 |
Decisions' Outcome: |
positivo |
Date of notification to the developer of the procedure outcomes: |
31/08/2022 |
Notification Reference number: |
MITE - 2022 - 104826 |
Outcome: |
positivo |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
75/10119 |
29/04/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/10119 |
Reference of previous authorization's Act: |
DVA-DEC-2011-121 del 28/03/2011 |
Application submission date: |
29/04/2019 |
Ministry Protocol Application submission: |
DVA/2019/10924 |
Ministry Protocol date of application submission: |
02/05/2019 |
Subject: |
Riesame complessivo dell'AIA |
Procedure starting date : |
13/05/2019 |
Launch of public consultation: |
15/05/2019 |
Deadline of submission of Public Comments on IPPC permit: |
14/06/2019 |
Decision Number: |
DM 513 |
Decision Date: |
12/12/2022 |
Date of notification to the developer of the procedure outcomes: |
21/12/2022 |
Notification Reference number: |
MITE - 2022 - 161621 |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
75/751 |
22/05/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/751 |
Application submission date: |
08/05/2014 |
Ministry Protocol Application submission: |
DVA-2014-0013704 |
Ministry Protocol date of application submission: |
12/05/2014 |
Subject: |
Ottemperanza prescrizione art.1, comma 5 "Trasmissione Piano di dismissione e messa in sicurezza dei gruppi di generazione elettrica turbogas PF3 PF4" |
Procedure starting date : |
22/05/2014 |
Decision Number: |
DVA-2015-0007479 |
Decision Date: |
17/03/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
75/741 |
17/04/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/741 |
Application submission date: |
28/03/2014 |
Ministry Protocol Application submission: |
DVA-2014-0009231 |
Ministry Protocol date of application submission: |
31/03/2014 |
Subject: |
Modifica non sostanziale per realizzazione di raccordi di tratti della rete fognaria acque meteoriche "chiare" c/o deposito oligrassi |
Procedure starting date : |
17/04/2014 |
IPPC Committee's opinion date: |
09/09/2015 |
Services Conference call date: |
09/09/2015 |
Decision Number: |
DVA-2015-0022604 |
Decision Date: |
08/09/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
75/346 |
10/05/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/346 |
Application submission date: |
26/04/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0010245 |
Ministry Protocol date of application submission: |
30/04/2012 |
Subject: |
Valutazione ottemperanza art.1, comma 3 del decreto AIA |
Procedure starting date : |
10/05/2012 |
Decision Number: |
DVA-2015-0005033 |
Decision Date: |
23/02/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
75/361 |
04/08/2011 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75/361 |
Application submission date: |
26/07/2011 |
Ministry Protocol Application submission: |
DVA - 2011 - 0019618 |
Ministry Protocol date of application submission: |
02/08/2011 |
Subject: |
Valutazione ottemperanza alle prescrizioni di cui al punto 9.12 comma a) e b) del Parere Istruttorio del Decreto |
Procedure starting date : |
04/08/2011 |
Decision Number: |
DVA - 2012 - 0014271 |
Decision Date: |
13/06/2012 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
First IPPC permit for existing installation |
|
75 |
04/10/2006 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
75 |
Application submission date: |
29/09/2006 |
Ministry Protocol Application submission: |
DSA-2006-0025348 |
Ministry Protocol date of application submission: |
04/10/2006 |
Date of request for integrations: |
09/03/2010 |
IPPC Committee's opinion date: |
24/11/2010 |
Services Conference call date: |
14/12/2010 |
Decision Number: |
DVA - DEC - 2011 - 0000121 |
Decision Date: |
28/03/2011 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |