IPPC permit’s reconsideration |
|
84/17405 |
31/12/2024 |
IPPC Technical Committee's assessment |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/17405 |
Reference of previous authorization's Act: |
DM n. 222 del 13/06/2024 |
Application submission date: |
31/12/2024 |
Ministry Protocol Application submission: |
prot. MASE/239536. |
Ministry Protocol date of application submission: |
31/12/2024 |
Subject: |
modifica del recapito dello scarico finale S3 e richiesta di rideterminazione delle prescrizioni n. 8 e 9 del DM n. 222 del 13/06/2024 |
Procedure starting date : |
15/01/2025 |
Launch of public consultation: |
15/01/2025 |
Deadline of submission of Public Comments on IPPC permit: |
14/02/2025 |
Stage of the Procedure: |
IPPC Technical Committee's assessment |
IPPC permit for non substantial changes |
|
84/16064 |
29/03/2024 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/16064 |
Reference of previous authorization's Act: |
DEC-MIN dell'8 maggio 2018, n. 158 |
Application submission date: |
28/03/2024 |
Ministry Protocol Application submission: |
prot. MASE/60658 |
Ministry Protocol date of application submission: |
29/03/2024 |
Subject: |
progetto "efficientamento dell'unità di deparaffinazione con propano |
Decision Number: |
DM 287 |
Decision Date: |
08/08/2024 |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/17002 |
16/09/2023 |
IPPC Technical Committee's assessment |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/17002 |
Reference of previous authorization's Act: |
D.M. n. 7 dell'8 gennaio 2021 |
Ministry Protocol Application submission: |
prot. MASE/166997 |
Ministry Protocol date of application submission: |
16/09/2023 |
Subject: |
riesame prescrizioni c) e g), contenute nel P.I.C. allegato al D.M. n. 7 dell'8 gennaio 2021 e inerenti agli interventi da attuare per l'adeguamento dei fondi dei serbatoi della Raffineria di Augusta |
Procedure starting date : |
11/10/2024 |
Launch of public consultation: |
11/10/2024 |
Deadline of submission of Public Comments on IPPC permit: |
10/11/2024 |
Stage of the Procedure: |
IPPC Technical Committee's assessment |
IPPC permit’s reconsideration |
|
84/14318 |
24/03/2023 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/14318 |
Reference of previous authorization's Act: |
DEC-MIN dell'8 maggio 2018, n. 158 |
Ministry Protocol Application submission: |
prot. MASE-2023-44970 |
Ministry Protocol date of application submission: |
24/03/2023 |
Procedure starting date : |
05/04/2023 |
Launch of public consultation: |
05/04/2023 |
Deadline of submission of Public Comments on IPPC permit: |
05/05/2023 |
Decision Number: |
DM 222 |
Decision Date: |
13/06/2024 |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/13679 |
30/11/2022 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/13679 |
Reference of previous authorization's Act: |
decreto dell'8 maggio 2018, n. 158 |
Ministry Protocol date of application submission: |
30/11/2022 |
Procedure starting date : |
01/12/2022 |
Launch of public consultation: |
01/12/2022 |
Deadline of submission of Public Comments on IPPC permit: |
31/12/2022 |
Decision Number: |
DM 222 |
Decision Date: |
13/06/2024 |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
84/10197 |
19/04/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/10197 |
Application submission date: |
19/04/2019 |
Ministry Protocol Application submission: |
DVA/2019/10152 |
Ministry Protocol date of application submission: |
19/04/2019 |
Subject: |
Riesame AIA per verifica ottemperanza a quanto prescritto nel PIC reso in data 10/01/2019 dalla Comm. AIA-IPPC |
Procedure starting date : |
24/05/2019 |
Decision Number: |
DM 45 |
Decision Date: |
26/01/2021 |
Decisions' Outcome: |
p0ositivo |
Date of notification to the developer of the procedure outcomes: |
02/02/2021 |
Notification Reference number: |
MATTM-2021-10602 |
Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for substantial changes |
|
84/9967 |
25/01/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/9967 |
Reference of previous authorization's Act: |
D.M. 158/2018 |
Application submission date: |
25/01/2019 |
Ministry Protocol Application submission: |
DVA/2019/1764 |
Ministry Protocol date of application submission: |
25/01/2019 |
Subject: |
Riesame parziale dell'AIA per adeguamento del quadro normativo a seguito dell'adozione del Piano Regionale di Tutela della Qualità dell'Aria in Sicilia |
Procedure starting date : |
05/06/2019 |
Launch of public consultation: |
11/03/2019 |
Deadline of submission of Public Comments on IPPC permit: |
10/04/2019 |
Date of notification to the developer of the procedure outcomes: |
13/10/2020 |
Notification Reference number: |
MATTM-2020-81021 |
Outcome: |
positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
84/9887 |
13/12/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/9887 |
Reference of previous authorization's Act: |
D.M. 158 del 2018 |
Application submission date: |
27/11/2018 |
Ministry Protocol Application submission: |
DVA/2018/28281 |
Ministry Protocol date of application submission: |
13/12/2018 |
Subject: |
Riesame avviato in ottemperanza a quanto prescritto dall'art. 1 comma 5 del provvedimento autorizzativo D.M. n. 158 dell' 8/05/2018 e dalla prescrizione n. 45 |
Procedure starting date : |
17/01/2019 |
Decision Number: |
DVA/2019/12677 |
Decision Date: |
20/05/2019 |
Decisions' Outcome: |
positivo |
Date of notification to the developer of the procedure outcomes: |
20/05/2019 |
Notification Reference number: |
DVA/2019/12677 |
Outcome: |
positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
84/9797 |
05/12/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/9797 |
Reference of previous authorization's Act: |
D.M. 158 del 2018 |
Application submission date: |
27/11/2018 |
Ministry Protocol Application submission: |
DVA/2018/27534 |
Ministry Protocol date of application submission: |
05/12/2018 |
Subject: |
Riesame avviato in ottemperanza a quanto prescritto dall'art. 1 comma 6 del provvedimento autorizzativo D.M. n. 158 e dalla prescrizione n. 46 del PIC. |
Decision Number: |
DM 07 |
Decision Date: |
08/01/2021 |
Decisions' Outcome: |
positivo |
Date of notification to the developer of the procedure outcomes: |
02/02/2021 |
Notification Reference number: |
MATTM-2021-10603 |
Outcome: |
positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
84/9681 |
27/09/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/9681 |
Reference of previous authorization's Act: |
D.M. 158 del 2018 |
Application submission date: |
27/09/2018 |
Ministry Protocol Application submission: |
DVA/2018/21695 |
Ministry Protocol date of application submission: |
27/09/2018 |
Subject: |
Riesame avviato in ottemperanza a quanto prescritto dall'art. 1, comma 4, del provvedimento autorizzativo D.M. n. 158 e prescrizione n. 7 del PIC. |
Procedure starting date : |
11/10/2018 |
Date of notification to the developer of the procedure outcomes: |
21/01/2019 |
Notification Reference number: |
DVA/2019/1246 |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/1182 |
01/02/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/1182 |
Application submission date: |
24/01/2018 |
Ministry Protocol Application submission: |
1731/DVA |
Ministry Protocol date of application submission: |
24/01/2018 |
Subject: |
interventi per diminuire delle emissioni diffuse di VOC associate al trattamento acque |
Procedure starting date : |
01/02/2018 |
Decision Number: |
4506/DVA |
Decision Date: |
22/02/2018 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/1136 |
23/03/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/1136 |
Application submission date: |
09/02/2017 |
Ministry Protocol Application submission: |
3050/DVA |
Ministry Protocol date of application submission: |
09/02/2017 |
Subject: |
riesame per inserimento nuovi limiti emissione da rispettare ai camini della SG151 e della nuova unità cogenerativa nuove prescrizioni VIA n. 14 del 25/01/2017 |
Procedure starting date : |
23/03/2017 |
Decision Number: |
13032/DVA |
Decision Date: |
01/06/2017 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/1061 |
15/04/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/1061 |
Reference of previous authorization's Act: |
DVA-DEC-2011-519 |
Application submission date: |
08/04/2016 |
Ministry Protocol Application submission: |
Decreto 137/DVA |
Ministry Protocol date of application submission: |
08/04/2016 |
Subject: |
Riesame complessivo |
Procedure starting date : |
15/04/2016 |
Decision Number: |
DM 158 |
Decision Date: |
22/03/2018 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/999 |
08/03/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/999 |
Application submission date: |
18/12/2015 |
Ministry Protocol Application submission: |
DVA-2015-31/12/2015 |
Ministry Protocol date of application submission: |
31/12/2015 |
Subject: |
Relazione di Riferimento |
Procedure starting date : |
08/03/2016 |
Decision Number: |
30868/DVA |
Decision Date: |
21/12/2016 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for substantial changes |
|
84/858 |
03/02/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/858 |
Application submission date: |
17/12/2014 |
Ministry Protocol Application submission: |
DVA-2015-0000547 |
Ministry Protocol date of application submission: |
09/01/2015 |
Subject: |
Richiesta di deroga di cui ai punti 3.3 e 3.4 della parte I Allegato II alla parte V del D.Lgs 152/06 |
Procedure starting date : |
03/02/2015 |
Decision Number: |
D.M. 301 |
Decision Date: |
23/12/2015 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
|
84/623 |
23/10/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/623 |
Application submission date: |
13/09/2013 |
Ministry Protocol Application submission: |
DVA-2013-0021493 |
Ministry Protocol date of application submission: |
20/09/2013 |
Subject: |
Richiesta da parte del Comune di Melilli di riesaminare il decreto AIA |
Procedure starting date : |
23/10/2013 |
IPPC Committee's opinion date: |
15/07/2014 |
Services Conference call date: |
18/09/2014 |
Decision Number: |
D.M. 250 |
Decision Date: |
25/11/2015 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
|
84/626 |
09/10/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/626 |
Application submission date: |
30/09/2013 |
Ministry Protocol Application submission: |
DVA-2013-0022780 |
Ministry Protocol date of application submission: |
07/10/2013 |
Subject: |
Valutazione ottemperanza art.1, comma 12 "Piano esecutivo per l'adozione delle MTD su tutti i serbatoi della Raffineria" |
Procedure starting date : |
09/10/2013 |
Decision Number: |
DVA-2015-0024613 |
Decision Date: |
01/10/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/435 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/435 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012 - 0024108 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Valutazione ottemperanza art.1, comma 3 del decreto Trasmissione studio finalizzato all'adozione delle Migliori Tecniche Disponobili di settore per l'unità FCC-CO. |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/436 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/436 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024125 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Valutazione ottemperanza art.1, comma 5 relazione tecnica + cronoprogramma degli interventi recupero vapori |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/437 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/437 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024097 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Valutazione ottemperazna art.1, comma 6 Progetto esecutivo, al fine di attenersi alle prescrizioni operative e gestionale di cui ai punti da a a k riportate a pag. 70 del parere istruttorio, relative al terminale di caricazione via terra ed al terminale marittimo. |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/438 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/438 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024159 |
Ministry Protocol date of application submission: |
09/10/2012 |
Subject: |
Ottemperanza art.1, comma 8 del decreto Studio di Fattibilità per l'installazione di sistemi di doppia tenuta su tutte le pompe che movimentano prodotti di vapore 1 bar a 38°C |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/439 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/439 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024100 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Ottemperanza art.1, comma 9 Progetto per l'istallazione di un impianto di recupero vapori presso i pontili della raffineria. |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/440 |
29/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/440 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024077 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Ottemperanza art.1,comma 10 Trasmissione studio di fattibilità per lo stoccaggio di petrolio greggio e di profìdotti della raffinazione con tensione di vapore superiore a 13mbar a 20°C |
Procedure starting date : |
29/10/2012 |
Decision Number: |
DVA-2013-0022864 |
Decision Date: |
08/10/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/441 |
24/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/441 |
Application submission date: |
27/09/2012 |
Ministry Protocol Application submission: |
DVA-2012-0024109 |
Ministry Protocol date of application submission: |
08/10/2012 |
Subject: |
Valutazione ottemperanza art.1, comma 11 Trasmissione piano per l'ottimizzazione del bilancio idrico di Raffineria, volto a minimizzare i prelievi d'acqua pozzi ed i flussi inviati ad impianto di trattamento IAS |
Procedure starting date : |
24/10/2012 |
Decision Number: |
DVA-2013-0016667 |
Decision Date: |
15/07/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/395 |
19/07/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/395 |
Application submission date: |
04/06/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0016390 |
Ministry Protocol date of application submission: |
09/07/2012 |
Subject: |
Modifica non sostanziale alla centrale termica per consentire la copertura dei consumi interni della raffineria fornendo in cogenerazione il vapore necessario alle utenze interne |
Procedure starting date : |
19/07/2012 |
IPPC Committee's opinion date: |
06/02/2013 |
Services Conference call date: |
14/02/2013 |
Decision Number: |
DEC/MIN/0000103 |
Decision Date: |
27/03/2013 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/366 |
22/06/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/366 |
Application submission date: |
30/03/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0008479 |
Ministry Protocol date of application submission: |
11/04/2012 |
Subject: |
Valutazione ottemperanza art.1, comma 7 del decreto "Studio di Fattibilità per l'installazione di bruciatori LOWNOx o Ultra Low Nox sui forni di raffineria" |
Procedure starting date : |
22/06/2012 |
Decision Number: |
DVA - 2013 - 0003130 |
Decision Date: |
06/02/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/330 |
29/03/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/330 |
Application submission date: |
21/02/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0004965 |
Ministry Protocol date of application submission: |
28/02/2012 |
Subject: |
Modifica non sostanziale al parco serbatoi "progetti Grezzi a Punta Cugno" |
Procedure starting date : |
29/03/2012 |
Decision Number: |
DVA - 2015 - 0025390 |
Decision Date: |
09/10/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
84/312 |
31/01/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84/312 |
Application submission date: |
22/12/2011 |
Ministry Protocol Application submission: |
DVA - 2011 - 0032667 |
Ministry Protocol date of application submission: |
30/12/2011 |
Subject: |
Valutazione ottemperanza prescrizione art.1, comma 4 "cronoprogramma dettagliato degli interventi di adeguamento sulla caldaia SG151 e di realizzazione del nuovo gruppo cogenerativo" |
Procedure starting date : |
31/01/2012 |
IPPC Committee's opinion date: |
17/09/2012 |
Services Conference call date: |
13/09/2012 |
Decision Number: |
DVA/2018/22064 |
Decision Date: |
17/09/2012 |
Date of notification to the developer of the procedure outcomes: |
17/09/2012 |
Notification Reference number: |
DVA/2018/22064 |
Stage of the Procedure: |
Concluded |
First IPPC permit for existing installation |
|
84 |
02/02/2007 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
84 |
Reference of previous authorization's Act: |
decreto dell'8 maggio 2018, n. 158 |
Application submission date: |
24/01/2007 |
Ministry Protocol Application submission: |
DSA-2007-0003254 |
Ministry Protocol date of application submission: |
02/02/2007 |
Date of request for integrations: |
19/03/2009 |
IPPC Committee's opinion date: |
08/06/2010 |
Services Conference call date: |
22/06/2010 |
Decision Number: |
DVA - DEC - 2011 - 0000519 |
Decision Date: |
16/09/2011 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |