Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Centrale Termoelettrica Federico II di Brindisi

General information

Installation: Centrale Termoelettrica Federico II di Brindisi

Localization: 72020 - Località Cerano

Installation type: Thermal power plant

Activity type: 1.1 - Impianti di combustione con potenza calorifica di combustione > 50 MW; 

Operator: Enel Produzione S.p.A.

Tax code: 05617841001

Installation status: Installazione in esercizio

Territories and marine areas

Regions: Puglia

Provinces: Brindisi

Municipalities: Brindisi

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
IPPC permit for non substantial changes 106/15925 26/02/2024 on-going procedure Procedure details Documents
IPPC permit for non substantial changes 106/11799 09/08/2021 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 106/11531 17/05/2021 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 106/11081 15/11/2020 Concluded Procedure details Documents
IPPC permit for substantial changes 106/10655 27/01/2020 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/10456 30/09/2019 Concluded Procedure details Documents
IPPC permit’s reconsideration 106/9932 31/01/2019 Concluded Procedure details Documents
IPPC permit for substantial changes 106/9840 12/12/2018 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/1193 05/04/2018 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 106/1183 15/02/2018 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 106/1170 10/11/2017 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/1146 01/06/2017 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/1121 08/02/2017 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/1108 05/12/2016 Concluded Procedure details Documents
IPPC permit’s reconsideration 106/1009 03/03/2016 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/959 11/12/2015 Concluded Procedure details Documents
IPPC permit’s reconsideration 106/937 21/09/2015 Concluded Procedure details Documents
IPPC permit’s reconsideration 106/871 05/03/2015 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/833 22/12/2014 Concluded Procedure details Documents
IPPC permit’s reconsideration 106/693 20/01/2014 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/594 23/08/2013 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/541 15/05/2013 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 106/484 17/01/2013 Concluded Procedure details Documents
IPPC permit for non substantial changes 106/455 09/11/2012 Concluded Procedure details Documents
First IPPC permit for existing installation 106 03/04/2007 Concluded Procedure details Documents