Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Centrale termoelettrica di Vado Ligure

General information

Installation: Centrale termoelettrica di Vado Ligure

Localization: 17047 - via Armando Diaz n.128

Installation type: Thermal power plant

Activity type: 1.1 - Impianti di combustione con potenza calorifica di combustione > 50 MW; 

Operator: TIRRENO POWER S.p.A.

Tax code: 07242841000

Installation status: Installazione in esercizio

Territories and marine areas

Regions: Liguria

Provinces: Savona

Municipalities: Quiliano

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
IPPC permit’s reconsideration 114/15418 12/12/2023 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/13537 10/10/2022 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 114/13169 08/08/2022 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 114/12370 16/02/2022 Concluded Procedure details Documents
IPPC permit for substantial changes 114/11934 27/10/2021 Concluded Procedure details Documents
IPPC permit’s reconsideration 114/10178 02/05/2019 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/10073 22/03/2019 Concluded Procedure details Documents
IPPC permit’s reconsideration 114/1149 07/06/2017 Concluded Procedure details Documents
IPPC permit’s reconsideration 114/1029 15/03/2016 on-going procedure Procedure details Documents
IPPC permit’s renewal 114/747 12/05/2014 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/710 04/02/2014 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/638 11/11/2013 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 114/601 23/08/2013 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/529 22/04/2013 Concluded Procedure details Documents
IPPC permit for non substantial changes 114/521 27/03/2013 Concluded Procedure details Documents
First IPPC permit for existing installation 114 08/02/2007 Concluded Procedure details Documents