Reconsideration of compliance to permit conditions |
|
134/865 |
02/03/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134/865 |
Application submission date: |
30/01/2015 |
Ministry Protocol Application submission: |
DVA-2015-0002821 |
Ministry Protocol date of application submission: |
02/02/2015 |
Subject: |
Piano di dismssione |
Procedure starting date : |
02/03/2015 |
Decision Number: |
DVA-2015-0026768 |
Decision Date: |
27/10/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
134/518 |
29/01/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134/518 |
Application submission date: |
20/12/2012 |
Ministry Protocol Application submission: |
DVA-2013-0000174 |
Ministry Protocol date of application submission: |
04/10/2013 |
Subject: |
Valutazione ottemperanza art.1, comma 5 del decreto AIA "Progetto riutilizzo biogas e proroga" |
Procedure starting date : |
29/01/2014 |
Decision Number: |
DVA-2015-0014009 |
Decision Date: |
26/05/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
134/517 |
21/03/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134/517 |
Application submission date: |
26/02/2013 |
Ministry Protocol Application submission: |
DVA-2013-0005671 |
Ministry Protocol date of application submission: |
06/03/2013 |
Subject: |
Modifica non sostanziale per la tempistica di installazione di alcuni SME |
Procedure starting date : |
21/03/2013 |
Decision Number: |
DVA-2015-0014009 |
Decision Date: |
26/05/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
134/323 |
07/03/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134/323 |
Application submission date: |
24/01/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0002642 |
Ministry Protocol date of application submission: |
02/02/2012 |
Subject: |
Richiesta di proroga per le Emissioni Nox e CO, modifica per la realizzazione del piping e della retocella di scarico a valle dei cristallizzatori, modifica del piping dell'azoto del reattore e eliminazione del camino E24 |
Procedure starting date : |
07/03/2012 |
Decision Number: |
DVA-2015-14009 |
Decision Date: |
26/05/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
|
134/324 |
06/03/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134/324 |
Application submission date: |
17/02/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0004684 |
Ministry Protocol date of application submission: |
23/02/2012 |
Subject: |
Valutazione ottemperanza prescrizione art.1, comma 3,4 e 6 del decreto AIA |
Procedure starting date : |
06/03/2012 |
Decision Number: |
DVA-2015-0014009 |
Decision Date: |
26/05/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
First IPPC permit for existing installation |
|
134 |
17/04/2007 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
134 |
Application submission date: |
30/03/2007 |
Ministry Protocol Application submission: |
DSA-2007-0011150 |
Ministry Protocol date of application submission: |
17/04/2007 |
Date of request for integrations: |
21/12/2009 |
IPPC Committee's opinion date: |
31/03/2011 |
Services Conference call date: |
13/04/2011 |
Decision Number: |
DVA - DEC - 2011 - 0000434 |
Decision Date: |
01/08/2011 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |