Off-shore wind farm of Chieuti (Foggia)
General information
Work: Off-shore wind farm of Chieuti (Foggia)
Project: Off-shore wind farm of Chieuti (Foggia)
Description: The project involves the construction of an offshore wind farm consisting of 50 wind turbines with a total rated power of 150 MW located in the sea in front of the municipalities of Serracapriola and Chieuti, and of the connections to the NTG.
Developer: Trevi Energy S.p.A.
Project type: Offshore wind farm
Deadline for submission of comments: 03/05/2008
mail
Territories and marine areas
Map
Regions: Puglia, Molise
Provinces: Campobasso, Foggia
Municipalities: Campomarino, Chieuti, Serracapriola
Marine areas: Mar Adriatico Meridionale, Mar Adriatico Centrale
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
|
317 |
13/02/2008 |
Suspended |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
317 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
13/02/2008 |
Publication date of the notice in newspapers: |
03/04/2008 |
Deadline of submission of Public Comments: |
03/05/2008 |
Date of request for documents perfection : |
04/03/2008 |
Date of perfection proceedings documents receipt: |
07/04/2008 |
Date of integrations receipt: |
08/04/2013 |
Date of the Opinion of the National Technical Commission : |
07/10/2010 |
National Technical Commission Opinion number: |
536 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Notes: |
Attivata procedura presso la Presidenza del Consiglio dei Ministri |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Suspended |