Gronda Est Milano: tratta Seregno-Bergamo
General information
Work: Gronda Ferroviaria Est Milano
Project: Gronda Est Milano: tratta Seregno-Bergamo
Developer: Italferr S.P.A.
Project type: Railways
Deadline for submission of comments: 28/11/2004
mail
Territories and marine areas
Regions: Lombardia
Provinces: Milano, Monza e della Brianza, Bergamo
Municipalities: Osio Sopra, Dalmine, Levate, Filago, Mezzago, Bottanuco, Macherio, Carnate, Trezzo sull'Adda, Vimercate, Lesmo, Sulbiate, Cornate d'Adda, Sovico, Capriate San Gervasio, Biassono, Usmate Velate
Marine areas: None
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
623 |
09/06/2003 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
623 |
Date of application submission: |
09/06/2003 |
Publication date of the notice in newspapers: |
07/07/2003 |
Deadline of submission of Public Comments: |
06/08/2003 |
Technical assessment starting date: |
05/09/2003 |
Date of request for integrations: |
03/10/2003 |
Date of integrations receipt: |
05/07/2004 |
Republication date of the notice in newspapers: |
29/10/2004 |
Deadline of submission of Public Comments on the republished project: |
28/11/2004 |
Republication subject
: |
Varianti plano-altimetriche |
Date of request for integrations for the republished project: |
18/02/2005 |
Date of integrations related to the republished project receipt: |
30/03/2005 |
Date of Special EIA Commission Opinion: |
10/05/2005 |
Special EIA Commission Opinion outcome: |
Positivo con prescrizioni |
Date of CIPE Deliberation: |
02/12/2005 |
CIPE Deliberation number : |
150 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
31/05/2006 |
Italian Republic Official Journal number : |
125 |
Notes: |
La ripubblicazione del progetto ha riguardato le varianti plano-altimetriche comprese tra le progressive dal Km 10+700 al Km 18+050 e dal Km 20+000 al Km 26+700. |
Stage of the Procedure: |
Concluded |