Environmental Impact Assessment |
|
7308 |
05/08/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
7308 |
Subject
: |
PROGETTO DI MANUTENZIONE STRAORDINARIA DELLA DIGA DI BADANA. PROROGA DM N. 189 DEL 25/07/2017 |
Date of application submission: |
05/08/2021 |
Date of the Opinion of the National Technical Commission : |
18/03/2022 |
National Technical Commission Opinion number: |
232 |
National Technical Commission Opinion outcome: |
Positivo |
Ministry of Cultural Heritage and Tourism Opinion date: |
21/03/2022 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
10867 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Positivo |
Date of the EIA Decree: |
30/05/2022 |
EIA Decree number: |
DM-2022-0000077 |
EIA Decree outcome: |
Positivo |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Screening |
|
3340 |
28/04/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3340 |
Date of application submission: |
28/04/2016 |
Publication date of the notice: |
04/05/2016 |
Deadline of submission of Public Comments: |
18/06/2016 |
Technical assessment starting date: |
05/05/2016 |
Date of integrations receipt: |
28/12/2016 |
Date of integrations second receipt: |
20/03/2017 |
Date of the Opinion of the National Technical Commission : |
19/05/2017 |
National Technical Commission Opinion number: |
2399 |
National Technical Commission Opinion outcome: |
Escluso dalla VIA con prescrizioni |
Determination date: |
30/05/2017 |
Determination number: |
DVA-DEC-2017-0000165 |
Determination outcome: |
Escluso dalla VIA con prescrizioni |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
|
3339 |
28/04/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3339 |
Subject
: |
Prescrizioni A.a, A.b, A.c, A.d, A.e, A.f, A.g, A.h del Decreto n. 400 del 18/07/2011 |
Date of application submission: |
28/04/2016 |
Technical assessment starting date: |
05/05/2016 |
Date of integrations receipt: |
28/12/2016 |
Date of integrations second receipt: |
20/03/2017 |
Date of the Opinion of the National Technical Commission : |
19/05/2017 |
National Technical Commission Opinion number: |
2401 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
29/05/2017 |
Determination number: |
DVA-DEC-2017-0000162 |
Determination outcome: |
Parzialmente ottemperata |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
|
314 |
08/07/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
314 |
Date of application submission: |
08/07/2009 |
Publication date of the notice in newspapers: |
29/06/2009 |
Deadline of submission of Public Comments: |
28/08/2009 |
Date of integrations receipt: |
22/04/2010 |
Republication date of the notice in newspapers: |
04/05/2010 |
Date of integrations related to the republished project receipt: |
28/09/2010 |
Date of the Opinion of the National Technical Commission : |
03/12/2010 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
18/07/2011 |
EIA Decree number: |
400 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notes: |
Il Decreto VIA DM-0000189 del 25/07/2017 modifica i termini di validità del Decreto VIA DVA-DEC-2011-0000400 del 18/07/2011, concedendo una proroga di 5 anni a decorrere dalla data di scadenza ovvero fino al 16/08/2021. |
Stage of the Procedure: |
Concluded |