EIA Follow-up (Strategic works Law 443/2001) |
2837 |
08/09/2014 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2837 |
Subject
: |
Linea Ferroviaria AV/AC Milano-Verona. Tratta Treviglio-Brescia. Progetto Esecutivo dell'Ingresso Urbano Interconnessione di Brescia Ovest. |
Date of application submission: |
08/09/2014 |
Date of integrations receipt: |
13/08/2018 |
Date of notification to the developer of the procedure outcomes: |
09/09/2020 |
Date of integrations second receipt: |
31/12/2018 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
06/11/2015 |
National Technical Commission Opinion number - Stage 1: |
1913 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
04/12/2015 |
Determination number - Stage 1 : |
DVA-DEC-2015-0000457 |
Determination outcome - Stage 1: |
Positivo |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
24/04/2020 |
National Technical Commission Opinion number - Stage 2: |
3380 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo con prescrizioni |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
03/09/2020 |
Determination number - Stage 2 : |
DET-264 |
Determination outcome - Stage 2: |
Positivo con prescrizioni |
Notification Reference number: |
69890 |
Outcome: |
Positivo con prescrizioni |
Notes: |
Determinazione direttoriale - Fase 2 (Monitoraggio ambientale ante operam ed in corso d'opera e rispetto prescrizioni) del 21/06/2017, prot. DVA-DEC-2017-0000189 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Unsubstantial project changes (Strategic works Law 443/2001) |
2834 |
13/08/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2834 |
Subject
: |
Varianti relative alla semplificazione delle lavorazioni interferenti con pubblici servizi/viabilità, affinamenti progettuali della fase esecutiva ed esigenze impiantistiche. |
Date of application submission: |
13/08/2014 |
Technical assessment starting date: |
18/09/2014 |
Date of notification to the developer of the procedure outcomes: |
05/12/2014 |
Date of the Opinion of the National Technical Commission : |
14/11/2014 |
National Technical Commission Opinion number: |
1653 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-2014-0040352 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
523 |
05/07/2010 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
523 |
Date of application submission: |
05/07/2010 |
Publication date of the notice in newspapers: |
02/07/2010 |
Deadline of submission of Public Comments: |
02/09/2010 |
Technical assessment starting date: |
19/07/2010 |
Date of request for integrations: |
26/08/2010 |
Date of integrations receipt: |
18/10/2010 |
Date of Special EIA Commission Opinion: |
04/02/2011 |
Special EIA Commission Opinion number: |
633 |
Special EIA Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
25/03/2011 |
Stage of the Procedure: |
Concluded |