380 kV double circuit power line Montecorvino-North Avellino and rationalization of the HV grid in the provinces of Avellino and Salerno


General information

Work: 380 kV double circuit power line Montecorvino-North Avellino and rationalization of the HV grid in the provinces of Avellino and Salerno

Project: 380 kV double circuit power line Montecorvino-North Avellino and rationalization of the HV grid in the provinces of Avellino and Salerno

Description: The project involves the construction of a new double circuit 380 kV overhead power line about 48 km long between the existing electrical station of Montecorvino and the proposed electrical station of North Avellino and new fittings to enable the streamlining of the HV grid in the provinces of Avellino and Salerno.

Developer: Terna Rete Elettrica Nazionale S.p.A.

Project type: Electrical power lines

Deadline for submission of comments: 04/06/2013 mail

Territories and marine areas

Map

Regions: Campania

Provinces: Avellino, Salerno

Municipalities: Montecorvino Rovella, Pratola Serra, Salza Irpina, Montoro Superiore, Grottolella, Santo Stefano del Sole, Serino, Manocalzati, Montefalcione, Santa Lucia di Serino, Mercato San Severino, Montecorvino Pugliano, Parolise, Altavilla Irpina, Candida, Giffoni Valle Piana, Baronissi, Cesinali, Fisciano, Atripalda, Montoro Inferiore, Prata di Principato Ultra, Aiello del Sabato, Solofra, Avellino, Sorbo Serpico, Montefredane

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 409 01/07/2010 Concluded Procedure details Documents