New Line HS /HC Venezia - Trieste. Ronchi - Trieste Section
General information
Work: Railway Line HS /HC Venice-Trieste
Project: New Line HS /HC Venezia - Trieste. Ronchi - Trieste Section
Description: The Ronchi - Trieste railway section is part of the project for the construction of the New Line HS/HC Venezia-Trieste. The route is 37 km long and runs for about 7 km above ground level alongside the existing historical line, while the rest of the route extends as variant to the historical line.
Developer: ITALFERR S.p.A
Project type: Railways
Deadline for submission of comments: 19/08/2012
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Nuova linea AV/AC Venezia-Trieste: tratta Ronchi dei Legionari-Trieste |
Italferr S.P.A. |
Environmental Impact Assessment (Strategic works Law 443/2001) |
Info Project and procedures
|
documents
|
New Line HS /HC Venezia - Trieste. Portogruaro - Ronchi dei Legionari Section |
ITALFERR S.p.A |
Environmental Impact Assessment (Strategic works Law 443/2001) |
Info Project and procedures
|
documents
|
New Line HS /HC Venezia - Trieste. Mestre-Marco Polo Airport Section |
ITALFERR S.p.A |
Environmental Impact Assessment (Strategic works Law 443/2001) |
Info Project and procedures
|
documents
|
New Line HS /HC Venezia - Trieste. Marco Polo Airport - Portogruaro Section |
ITALFERR S.p.A |
Environmental Impact Assessment (Strategic works Law 443/2001) |
Info Project and procedures
|
documents
|
Territories and marine areas
Map
Regions: Friuli Venezia Giulia
Provinces: Gorizia, Trieste
Municipalities: Trieste, Staranzano, San Canzian d'Isonzo, Ronchi dei Legionari, Doberdo' del Lago, Monfalcone, Duino-Aurisina, Turriaco
Marine areas: None
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
445 |
22/12/2010 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
445 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
22/12/2010 |
Publication date of the notice in newspapers: |
22/12/2010 |
Deadline of submission of Public Comments: |
20/02/2011 |
Technical assessment starting date: |
28/12/2011 |
Republication date of the notice in newspapers: |
20/06/2012 |
Deadline of submission of Public Comments on the republished project: |
19/08/2012 |
Republication subject
: |
Deposito degli elaborati relativi al "Sistema Conoscitivo Unico dei Quattro Tracciati di Progetto" |
Date of request for integrations for the republished project: |
18/10/2012 |
Date of integrations related to the republished project receipt: |
18/06/2013 |
Date of the Opinion of the National Technical Commission : |
29/04/2016 |
National Technical Commission Opinion number: |
2060 |
National Technical Commission Opinion outcome: |
Negativo |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
10/05/2016 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |