Reorganization of the high voltage electrical grid in the metropolitan area of Rome - Northwest Quadrant
General information
Work: Reorganization of the high voltage electrical grid in the metropolitan area of Rome
Project: Reorganization of the high voltage electrical grid in the metropolitan area of Rome - Northwest Quadrant
Description: The Reorganization of the HV Electrical Grid in the metropolitan area of Rome Northwest Quadrant involves the construction of 380 kV North Rome - Flaminia - West Rome, the 150 kV power line West Rome - Primavalle - La Storta - Flaminia, the 150 kV power line North Rome - Transition Bufalotta, the 380 kV North-Rome - Montalto and 150 kV West Rome - Fiano overhead power lines , the 150 kV overhead variant of Acea Flaminia - Acea Orte and the demolition of 105.94 km of overhead lines.
Developer: Terna Rete Elettrica Nazionale S.p.A.
Project type: Electrical power lines
Deadline for submission of comments: 16/06/2014
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Reorganization of the electricity network HV/ UHV in the metropolitan area of Rome - Southwest Quadrant |
Terna Rete Elettrica Nazionale S.p.A. |
EIA Compliance |
Info Project and procedures
|
documents
|
Riassetto della Rete Elettrica AT nell'area metropolitana di Roma Quadrante Sud Ovest-Variante viabilità di accesso alla stazione elettrica e tracciato cavi 150kV |
Terna S.p.A. |
Preliminary assessment |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Lazio
Provinces: Roma
Municipalities: Formello, Sacrofano, Roma
Marine areas: None
Select procedure
Procedure |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
449 |
02/05/2011 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
449 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
02/05/2011 |
Publication date of the notice in newspapers: |
29/04/2011 |
Deadline of submission of Public Comments: |
28/06/2011 |
Technical assessment starting date: |
08/09/2011 |
Date of integrations receipt: |
26/03/2012 |
Date of second request for integrations : |
24/05/2013 |
Date of integrations second receipt: |
10/04/2014 |
Republication date of the notice in newspapers: |
17/04/2014 |
Deadline of submission of Public Comments on the republished project: |
16/06/2014 |
Date of the EIA Decree: |
23/02/2017 |
EIA Decree number: |
DVA-2017-0004268 |
EIA Decree outcome: |
Archiviata |
Notes: |
Con nota del 22/06/2016 (prot. DVA-2016-0016633) è stata concessa una sospensione del procedimento di 45 giorni. Con nota del 28/04/2016 (prot. DVA-2016-0011486) è stata concessa una sospensione del procedimento di 45 giorni. Con nota del 14/01/2014 (prot. DVA-2014-0000585) è stata concessa una ulteriore proroga di 90 giorni per la consegna delle integrazioni. Con nota del 30/10/2013 (prot. DVA-2013-0024842) è stata concessa una ulteriore proroga di 60 giorni per la consegna delle integrazioni. Con nota del 19/07/2013 (prot. DVA-2013_0017055) è stata concessa una sospensione del procedimento di 120 giorni per la presentazione delle integrazioni |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |