EIA Compliance (Strategic works Law 443/2001) |
|
12941 |
01/08/2024 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
12941 |
Date of application submission: |
01/08/2024 |
Date of perfection proceedings documents receipt: |
16/09/2024 |
Technical assessment starting date: |
27/09/2024 |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Unsubstantial project changes (Strategic works Law 443/2001) |
|
10970 |
05/01/2024 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10970 |
Subject
: |
Collegamento autostradale Dalmine-Como-Varese-Valico del Gaggiolo e opere ad esso connesse Tratte B2 - C. (CUP F11B06000270007). |
Date of application submission: |
05/01/2024 |
Technical assessment starting date: |
22/02/2024 |
Notification date: |
27/05/2024 |
Notification Reference number: |
MASE_2024-0096841 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
10825 |
21/12/2023 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10825 |
Subject
: |
Collegamento autostradale Dalmine-Como-Varese. Valico del Gaggiolo e opere ad esso connesse. Progetto esecutivo Tratte B2 - C |
Date of application submission: |
21/12/2023 |
Date of request for documents perfection : |
01/02/2024 |
Date of perfection proceedings documents receipt: |
16/02/2024 |
Technical assessment starting date: |
11/03/2024 |
Date of the Opinion of the National Technical Commission on usage Plan: |
30/04/2024 |
Opinion number of the National Technical Commission on usage Plan: |
CTVA_2024-0006101 |
Opinion outcome of the National Technical Commission on usage Plan: |
Positivo |
Usage Plan Determination date: |
27/05/2024 |
Determination number on usage Plan: |
MASE_VA_DEC_2024-0000159 |
Usage Plan Determination outcome: |
Positivo |
Notification date: |
27/05/2024 |
Notification Reference number: |
MASE_2024-0097399 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Approved with/without prescriptions |
EIA Follow-up (Strategic works Law 443/2001) |
|
10710 |
13/12/2023 |
Pending the start of the enivronmental monitoring
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10710 |
Subject
: |
Collegamento Autostradale tra Dalmine, Como, Varese, Valico del Gaggiolo ed opere ad esso connesse (Autostrada Pedemontana Lombarda). Progetto Esecutivo Tratte B2 - C |
Date of application submission: |
13/12/2023 |
Notification date: |
20/05/2024 |
Notification Reference number: |
MASE_2024-0091991 |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Pending the start of the enivronmental monitoring
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
10268 |
10/08/2023 |
Suspended by request of the developer |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10268 |
Subject
: |
Progetto definitivo della Variante della tratta D dell'Autostrada Pedemontana Lombarda A36 |
Date of application submission: |
10/08/2023 |
Data avvio consultazione pubblica: |
20/09/2023 |
Deadline of submission of Public Comments: |
19/11/2023 |
Date of request for documents perfection : |
31/08/2023 |
Date of perfection proceedings documents receipt: |
06/09/2023 |
Date of request for integrations: |
24/05/2024 |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Suspended by request of the developer |
Unsubstantial project changes (Strategic works Law 443/2001) |
|
2801 |
10/07/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2801 |
Subject
: |
Progetto Esecutivo tratta B1-Galleria artificiale |
Date of application submission: |
10/07/2014 |
Technical assessment starting date: |
24/07/2014 |
Date of notification to the developer of the procedure outcomes: |
11/01/2016 |
Date of the Opinion of the National Technical Commission : |
18/12/2015 |
National Technical Commission Opinion number: |
1956 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-DEC-2016-0000001 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
2190 |
07/01/2013 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2190 |
Subject
: |
Collegamento autostradale Dalmine-Como-Varese-Valico del Gaggiolo e opere ad esso connesse. Progetto Esecutivo - 6° e 8° stralcio |
Date of application submission: |
07/01/2013 |
Date of notification to the developer of the procedure outcomes: |
18/08/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
14/03/2014 |
National Technical Commission Opinion number - Stage 1: |
1465 |
National Technical Commission Opinion outcome - Stage 1: |
Negativo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
02/05/2014 |
Determination number - Stage 1 : |
DVA-2014-0012571 |
Determination outcome - Stage 1: |
Negativo |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
31/07/2020 |
National Technical Commission Opinion number - Stage 2: |
DEC-239 |
National Technical Commission Opinion outcome - Stage 2: |
Negativo |
Notification Reference number: |
64846 |
Outcome: |
Negativo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Compliance (Strategic works Law 443/2001) |
|
1978 |
02/07/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1978 |
Subject
: |
VO sullo Svincolo di Gazzada Schianno. Prescrizioni 39, 40, 243 della Delibera CIPE n.97 del 06/11/2009 |
Date of application submission: |
02/07/2012 |
Technical assessment starting date: |
12/07/2012 |
Date of integrations receipt: |
13/08/2012 |
Date of the Opinion of the National Technical Commission : |
26/10/2012 |
National Technical Commission Opinion number: |
1076 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
21/11/2012 |
Determination number: |
DVA_2012-0028131 |
Determination outcome: |
Ottemperata |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
1679 |
25/11/2011 |
Concluded |
Procedure details
|
|
Procedure Code (ID_VIP/ID_MATTM) |
1679 |
Subject
: |
Collegamento autostradale Dalmine - Como - Varese - Valico del Gaggiolo ed opere connesse (Pedemontana Lombarda). Svincolo di Lomazzo, ottemperanza alla prescrizione n. 241 della Delibera CIPE n. 97/2009 |
Date of application submission: |
25/11/2011 |
Date of notification to the developer of the procedure outcomes: |
01/08/2012 |
Notification Reference number: |
DVA-2012_0018564 |
Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
477 |
19/02/2010 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
477 |
Subject
: |
1°, 2°, 3°, 4° e 5° stralcio - Collegamento autostradale Dalmine - Como - Varese - Valico del Gaggiolo ed opere connesse. (Pedemontana Lombarda) |
Date of application submission: |
19/02/2010 |
Date of notification to the developer of the procedure outcomes: |
15/09/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
11/10/2013 |
National Technical Commission Opinion number - Stage 1: |
1357 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
20/11/2013 |
Determination number - Stage 1 : |
DVA-2013-0026678 |
Determination outcome - Stage 1: |
Positivo |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
23/04/2020 |
National Technical Commission Opinion number - Stage 2: |
PRR-3353-23042020 |
National Technical Commission Opinion outcome - Stage 2: |
Negativo |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
03/09/2020 |
Determination number - Stage 2 : |
DET-265 |
Determination outcome - Stage 2: |
Negativo |
Notification Reference number: |
7160 |
Outcome: |
Negativo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
126 |
29/04/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
126 |
Date of application submission: |
29/04/2009 |
Publication date of the notice in newspapers: |
21/04/2009 |
Deadline of submission of Public Comments: |
28/06/2009 |
Technical assessment starting date: |
15/05/2009 |
Date of Special EIA Commission Opinion: |
29/07/2009 |
Special EIA Commission Opinion number: |
328 |
Special EIA Commission Opinion outcome: |
Positivo con pescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
15/09/2009 |
Date of CIPE Deliberation: |
06/11/2009 |
CIPE Deliberation number : |
97 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
647 |
05/02/2004 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
647 |
Date of application submission: |
05/02/2004 |
Publication date of the notice in newspapers: |
04/02/2004 |
Deadline of submission of Public Comments: |
05/03/2004 |
Technical assessment starting date: |
21/04/2004 |
Republication date of the notice in newspapers: |
03/12/2004 |
Deadline of submission of Public Comments on the republished project: |
02/01/2005 |
Republication subject
: |
Integrazioni e modifiche: Tratta B1 (ex B) e tratta B2 nuova |
Date of Special EIA Commission Opinion: |
08/03/2005 |
Special EIA Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
06/05/2005 |
Date of CIPE Deliberation: |
29/03/2006 |
CIPE Deliberation number : |
77 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
23/11/2006 |
Italian Republic Official Journal number : |
219 |
Stage of the Procedure: |
Concluded |