General information

Work: HS/HC Milano-Genova railway

Project: HS/HC Milano-Genova "Terzo Valico dei Giovi" railway

Description: The HS/HC Milano-Genova "Terzo Valico dei Giovi" railway starts from Genova Node and develops along the Genova-Milano line, to Tortona, and along the Alessandria-Torino line, to Novi Ligure. The track covers an overall distance of 53 km of which 36 km in tunnels, and is connected to the existing line through four interconnections 25 km long.

Developer: Rete Ferroviaria Italiana S.p.A.

Project type: Railways

Unique code (CUP): F81H92000000008

Related website: Osservatorio Ambientale Linea AV/AC Milano-Genova "Terzo Valico dei Giovi"

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Liguria, Piemonte

Provinces: Genova, Alessandria

Municipalities: Genova, Arquata Scrivia, Serravalle Scrivia, Carrosio, Pozzolo Formigaro, Novi Ligure, Tortona, Fraconalto, Gavi, Voltaggio, Ceranesi, Campomorone

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
EIA Follow-up (Strategic works Law 443/2001) 9620 21/03/2023 Administrative control Procedure details
Unsubstantial project changes (Strategic works Law 443/2001) 9421 02/02/2023 Concluded Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 8515 22/06/2022 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 6027 16/04/2021 Administrative control Procedure details
Unsubstantial project changes (Strategic works Law 443/2001) 5623 22/10/2020 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 4455 15/01/2019 Pending the start of the enivronmental monitoring Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 4223 06/08/2018 Concluded Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 3973 12/03/2018 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 3635 12/06/2017 Pending the start of the enivronmental monitoring Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 3330 18/04/2016 Concluded Procedure details Documents
Environmental Impact Assessment (Strategic works Law 443/2001) 3274 01/02/2016 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 3103 24/08/2015 Concluded Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 3097 07/08/2015 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2981 26/03/2015 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2957 11/02/2015 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2864 10/10/2014 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2831 13/08/2014 Concluded Procedure details Documents
Unsubstantial project changes (Strategic works Law 443/2001) 2810 01/08/2014 Concluded Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2668 21/02/2014 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 2194 29/01/2013 Concluded Procedure details Documents
Environmental Observatory 14/09/2012 - Procedure details
EIA Compliance (Strategic works Law 443/2001) 764 19/09/2005 Concluded Procedure details Documents
Environmental Impact Assessment (Strategic works Law 443/2001) 601 10/03/2003 Concluded Procedure details Documents