Treviso Antonio Canova Airport - Master Plan (2011-2030)
General information
Work: Treviso Airport
Project: Treviso Antonio Canova Airport - Master Plan (2011-2030)
Description: Treviso Antonio Canova Airport’s Master Plan provides for the extension of the passenger terminal, work on the access system - roads and car parks, on flight infrastructures, on the networks and installations in order to meet the growth in air traffic
Developer: ENAC - Ente Nazionale per l'Aviazione Civile
Project type: Airports
Deadline for submission of comments: 30/04/2013
mail
Other projects related to the same work: Show / Hide
Territories and marine areas
Map
Regions: Veneto
Provinces: Treviso
Municipalities: Quinto di Treviso, Treviso
Marine areas: None
Select procedure
Procedure |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
1799 |
13/03/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1799 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
13/03/2012 |
Publication date of the notice in newspapers: |
09/03/2012 |
Deadline of submission of Public Comments: |
12/05/2012 |
Technical assessment starting date: |
04/04/2012 |
Date of integrations receipt: |
24/10/2012 |
Date of integrations second receipt: |
28/02/2013 |
Republication date of the notice in newspapers: |
01/03/2013 |
Deadline of submission of Public Comments on the republished project: |
30/04/2013 |
Republication subject
: |
Integrazioni volontarie |
Date of the Opinion of the National Technical Commission : |
01/08/2014 |
National Technical Commission Opinion number: |
1590 |
National Technical Commission Opinion outcome: |
Negativo |
Date of the EIA Decree: |
06/07/2015 |
EIA Decree number: |
DVA-2015-0017491 |
EIA Decree outcome: |
Archiviato |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225903 - cress-5@minambiente.it |
Stage of the Procedure: |
Concluded |