EIA Follow-up (Strategic works Law 443/2001) |
8462 |
20/05/2022 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8462 |
Date of application submission: |
20/05/2022 |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Follow-up (Strategic works Law 443/2001) |
8460 |
20/05/2022 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8460 |
Subject
: |
Itinerario Ragusa Catania. Collegamento viario compreso tra lo svincolo della S.S. 514 di Chiaramonte con la S.S. 115 e lo svincolo della S.S. 194 "Ragusana". Progetto esecutivo Lotto 2 dallo svincolo n. 3 sulla S.P. 5 (compreso) allo svincolo n. 5"Grammichele" (escluso), ca km 12,34. |
Date of application submission: |
20/05/2022 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Follow-up (Strategic works Law 443/2001) |
8459 |
20/05/2022 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8459 |
Subject
: |
Itinerario Ragusa Catania. Collegamento viario compreso tra lo svincolo della S.S. 514 di Chiaramonte con la S.S. 115 e lo svincolo della S.S. 194 "Ragusana". Progetto esecutivo Lotto 1 dallo svincolo n. 1 sulla S.S. 115 (compreso) allo svincolo n. 3 sulla S.P. 5 escluso, ca km 18,18. |
Date of application submission: |
20/05/2022 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Follow-up (Strategic works Law 443/2001) |
8461 |
20/05/2022 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8461 |
Subject
: |
Itinerario Ragusa Catania. Collegamento viario compreso tra lo svincolo della S.S. 514 di Chiaramonte con la S.S. 115 e lo svincolo della S.S. 194 "Ragusana". Progetto esecutivo Lotto 3 dallo svincolo n. 5 "Grammichele" (compreso) allo svincolo n. 8 "Francofonte" (escluso), ca km 18,52. |
Date of application submission: |
20/05/2022 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Compliance (Strategic works Law 443/2001) |
3602 |
06/04/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3602 |
Subject
: |
Progetto Definitivo del collegamento viario con caratteristiche autostradali compreso tra lo svincolo della S.S. 514 "di Chiaramonte" con la S.S. 115 e lo svincolo della S.S. 194 "Ragusana" con la S.S. 114 |
Date of application submission: |
06/04/2017 |
Technical assessment starting date: |
18/04/2017 |
Date of integrations receipt: |
07/08/2017 |
Date of integrations second receipt: |
18/09/2017 |
Date of the Opinion of the National Technical Commission : |
10/11/2017 |
National Technical Commission Opinion number: |
2550 |
National Technical Commission Opinion outcome: |
Parzialmente Ottemperata |
Determination date: |
20/11/2017 |
Determination number: |
DVA-DEC-2017-0000349 |
Determination outcome: |
Parzialmente Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
137 |
03/03/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
137 |
EIA-AA integrated Procedure : |
Sì |
Subject
: |
Variazione progetto preliminare rispetto a quello approvato parzialmente con Delibere CIPE 79/2006 e 51/2007 e verifica di ottemperanza alle prescrizioni impartite dalle medesime Delibere. |
Date of application submission: |
03/03/2009 |
Technical assessment starting date: |
23/03/2009 |
Date of the Opinion of the National Technical Commission : |
25/06/2009 |
National Technical Commission Opinion number: |
302 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
31/07/2009 |
Date of CIPE Deliberation: |
22/01/2010 |
CIPE Deliberation number : |
3 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
06/08/2010 |
Italian Republic Official Journal number : |
182 |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
658 |
02/09/2004 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
658 |
Date of application submission: |
02/09/2004 |
Publication date of the notice in newspapers: |
27/08/2004 |
Deadline of submission of Public Comments: |
26/09/2004 |
Technical assessment starting date: |
16/02/2005 |
Date of request for integrations: |
18/03/2005 |
Date of integrations receipt: |
26/04/2005 |
Date of Special EIA Commission Opinion: |
06/09/2005 |
Special EIA Commission Opinion outcome: |
Positivo con prescrizioni per la tratta dalla progressiva Km 36+000 alla fine del tracciato |
Date of CIPE Deliberation: |
29/03/2006 |
CIPE Deliberation number : |
79 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
25/08/2006 |
Italian Republic Official Journal number : |
197 |
Notes: |
In data 06/09/2005, per il tratto dalla progressiva Km 1+500 alla progressiva Km 36+000, è stato espresso parere negativo salvo l'adeguamento del tracciato in sede di progetto definitivo. |
Stage of the Procedure: |
Concluded |