Work: Monfalcone power plant

Project: Progetto di modifica della centrale termoelettrica di Monfalcone (GO)

Description: Il progetto prevede l'installazione di un nuovo ciclo combinato di ultima generazione, da circa 860 MWe lordi, alimentato a gas naturale, composto da un turbogas da circa 579 MWe di classe "H" (TG52), un generatore di vapore a recupero(GVR52) e una turbina a vapore da circa 280 MWe (TV51).

Developer: A2A Energiefuture S.p.A.

Project type: Thermal power plant

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Friuli Venezia Giulia

Provinces: Gorizia

Municipalities: Monfalcone

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
EIA Compliance 10764 05/04/2024 Administrative control Procedure details Documents
EIA Compliance 11263 12/03/2024 Administrative control Procedure details Documents
EIA Compliance 11262 11/03/2024 Decision being prepared Procedure details Documents
EIA Compliance 11261 11/03/2024 Administrative control Procedure details Documents
EIA Compliance 11121 16/01/2024 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 10771 20/12/2023 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 10769 15/12/2023 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 10767 14/12/2023 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 11146 27/09/2023 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 9940 06/09/2022 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 11147 18/07/2022 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 8669 18/07/2022 EIA-SEA Technical Committee's assessment Procedure details Documents
Environmental Impact Assessment 5071 18/12/2019 Concluded Procedure details Documents