Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Centrale termoelettrica da 750 MW di Modugno (BA)


General information

Work: Centrale termoelettrica di Modugno (BA)

Project: Centrale termoelettrica da 750 MW di Modugno (BA)

Developer: Energia S.p.A.

Project type: Thermal power plant

Other projects related to the same work: Show / Hide

Territories and marine areas

Regions: Puglia

Provinces: Bari

Municipalities: Modugno

Marine areas: None

Select procedure

Procedure Online application code Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 395 18/04/2002 Concluded Procedure details Documents