EIA Compliance (PNIEC-PNRR) |
|
10899 |
10/01/2024 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10899 |
Subject
: |
Nuovo Collegamento Palermo - Catania, tratta Caltanissetta Xirbi - Nuova Enna (Lotto 4A) - CUP J11H03000180001. Piano di Utilizzo delle Terre e rocce da scavo (PUT) di Progetto Esecutivo delle opere di Parte B, in ottemperanza alla condizione ambientale n. 6 del parere n. 2 del 29/4/22 della CT PNRR-PNIEC (D.M. 84 del 31/05/2023). |
Date of application submission: |
10/01/2024 |
Date of request for Observatory integrations: |
01/03/2024 |
Date of Observatory integrations receipt: |
24/04/2024 |
Determination date: |
30/05/2024 |
Determination number: |
MASE_VA_DEC_2024-0000168 |
Determination outcome: |
Positivo |
Notification date: |
03/06/2024 |
Notification Reference number: |
MASE_2024-0101745 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Approved with/without prescriptions |
EIA Compliance (PNIEC-PNRR) |
|
9987 |
03/07/2023 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
9987 |
Subject
: |
Nuovo Collegamento Palermo - Catania, tratta Caltanissetta Xirbi - Nuova Enna (Lotto 4A) - CUP J11H03000180001. Piano di Utilizzo delle Terre e rocce da scavo (PUT) di Progetto Esecutivo delle opere di Parte A, in ottemperanza alla condizione ambientale n. 6 del parere n. 2 del 29/4/22 della CT PNRR-PNIEC (D.M. 84 del 31/05/2023). |
Date of application submission: |
03/07/2023 |
Date of the Opinion of the CTPNRR-PNIEC: |
26/10/2023 |
CTPNRR-PNIEC Opinion number: |
5 |
CTPNRR-PNIEC Opinion outcome: |
Concluso |
Determination date: |
07/12/2023 |
Determination number: |
MASE_VA_DEC_2023-0000648 |
Determination outcome: |
Concluso |
Notification date: |
18/12/2023 |
Notification Reference number: |
MASE_2023-0207651 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Approved with/without prescriptions |
Environmental Impact Assessment (PNIEC-PNRR) |
|
7647 |
22/11/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
7647 |
Subject
: |
Progetto definitivo della Direttrice ferroviaria Messina-Catania-Palermo, Nuovo collegamento Palermo-Catania. Lotto 4A: tratta Caltanissetta Xirbi-Nuova Enna |
Date of application submission: |
22/11/2021 |
Data avvio consultazione pubblica: |
26/01/2022 |
Deadline of submission of Public Comments: |
25/02/2022 |
Date of request for documents perfection : |
29/11/2021 |
Date of request for integrations: |
15/03/2022 |
Data comunicazione avvio nuova consultazione pubblica: |
17/03/2022 |
Deadline of submission of Public Comments on the republished project: |
01/04/2022 |
Ministry of Cultural Heritage and Tourism Opinion date: |
05/05/2022 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
0055420 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Favorevole |
Date of the EIA Decree: |
30/05/2022 |
EIA Decree number: |
MiTE- 2022-0000084 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notification date: |
08/06/2022 |
Notification Reference number: |
MiTE_2022-0071225 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |