Rationalization of the high voltage electricity grid in the area of Val Formazza and Interconnector Italy-Switzerland
General information
Work: Rationalization of the high voltage electricity grid in the area of Val Formazza and Interconnector Italy-Switzerland
Project: Rationalization of the high voltage electricity grid in the area of Val Formazza and Interconnector Italy-Switzerland
Description: The Rationalization of the high voltage electricity grid in the area of Val Formazza and Interconnector Italy-Switzerland involves the construction of overhead/underground power line 226 km long and the demolition of 176 km of existing electrical lines in order to improve the reliability of the electrical system at regional level and to increase the transport capacity between Italy and Switzerland.
Developer: Terna Rete Elettrica Nazionale S.p.A.
Project type: Electrical power lines
Deadline for submission of comments: 24/08/2018
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Razionalizzazione della rete a 220 kV della Val Formazza. Procedimento di VIA ai sensi dell'art.23 del D.Lgs. 152/2006. |
Terna S.p.A. |
Environmental Impact Assessment |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Piemonte, Lombardia
Provinces: Milano, Novara, Verbano-Cusio-Ossola
Municipalities: Massino Visconti, Veruno, Ornavasso, Divignano, Turbigo, Pallanzeno, Gignese, Bareggio, Vittuone, Villadossola, Domodossola, Marano Ticino, Baceno, Vogogna, Marcallo con Casone, Bernate Ticino, Arona, Cameri, Baveno, Gravellona Toce, Castano Primo, Premosello-Chiovenda, Cuggiono, Crodo, Stresa, Mergozzo, Boffalora sopra Ticino, Nebbiuno, Bellinzago Novarese, Magenta, Formazza, Meina, Crevoladossola, Settimo Milanese, Nosate, Verbania, Masera, Beura-Cardezza, Mezzomerico, Brovello-Carpugnino, Cornaredo, Premia, Trontano, Santo Stefano Ticino, Comignago, Mesero, Anzola d'Ossola, Oleggio, Corbetta, Agrate Conturbia, Cusago, Robecchetto con Induno, Montecrestese, Sedriano
Marine areas: None
Select procedure
Procedure |
Online application code |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
|
1897 |
10/05/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1897 |
Transboundary consultations: |
In data 29/09/2014 il Ministero degli Affari Esteri e della Cooperazione Internazionale ha notificato l'avvio della Procedura VIA ai sensi della Convenzione di Espoo alla Svizzera con richiesta di esprimere il proprio interesse a partecipare alla consultazione transfrontaliera |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
10/05/2012 |
Publication date of the notice in newspapers: |
08/05/2012 |
Deadline of submission of Public Comments: |
09/07/2012 |
Technical assessment starting date: |
08/06/2012 |
Date of request for integrations: |
04/09/2012 |
Date of integrations receipt: |
18/09/2012 |
Date of integrations second receipt: |
05/06/2014 |
Republication date of the notice in newspapers: |
04/06/2014 |
Deadline of submission of Public Comments on the republished project: |
03/08/2014 |
Republication subject
: |
Documentazione integrativa |
Date of request for integrations for the republished project: |
07/08/2015 |
Date of integrations related to the republished project receipt: |
11/01/2017 |
Second Republication date: |
06/02/2017 |
Deadline of submission of Public Comments - Second republication: |
07/04/2017 |
Second republication subject
: |
Documentazione integrativa |
Date of integrations receipt - Second republication: |
06/04/2017 |
Third Republication date: |
16/06/2018 |
Deadline of submission of Public Comments - Third republication: |
24/08/2018 |
Communication date of the outcome to the developer: |
09/12/2021 |
Protocol of outcome communication to the developer: |
MATTM_2021-0137822 |
Outcome: |
Archiviata |
Notes: |
Con nota del 22/01/2018 (prot. DVA-2018-0001484) è stata concessa una sospensione del procedimento fino al 31/05/2018. Con nota del 24/02/2016 (prot. DVA-2016-0004757) è stata concessa una sospensione del procedimento di 10 mesi. Con nota del 23/09/2015 (prot. DVA-2015-0023867) è stata concessa una proroga di 150 giorni per la consegna delle integrazioni. In data 10/05/2012 e' stato presentato il progetto Razionalizzazione rete Alta Tensione nella Val Formazza. In data 05/06/2014 il Progetto e' stato integrato con l'intervento Interconnector Italia-Svizzera. Con nota del 11.06.2018 Terna ha consegnato una copia completa degli elaborati attualmente validi, pubblicati in data 18.06.2018, comprensivi delle ultime integrazioni del 31/05/2018. |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |