28/01/2015
The Project Change determination (DVA-2015-0002470 of 28 January 2015) related to E78 Grosseto - Fano motorway, section Grosseto-Siena. Extension to four lane of the S.S. 223 from km 30+040 to km 41+600. Lots 5,6,7,8. Variant of reinforced soil walls, has been issued with unfavourable outcome.
28/01/2015
The EIA compliance determination (DVA-2015-0001940 of 22 January 2015) on the prescriptions 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11 of the EIA Screening determination no. 24312 of 10 October 2012 has been issued with partly favourable outcome.
22/01/2015
The EIA compliance determination (DVA-2015-0001940 of 22 January 2015) on the prescription A29 (2013 environmental monitoring) of the EIA decision no. 1050 of 8 September 2009 has been issued with favourable outcome.
21/01/2015
The Project Change determination (DVA-2015-0001739 of 21 January 2015) related to Road link between Marche and Umbria and Quadrilatero di penetrazione. Maxi Lot 1. Sub lot 1.2. Final disposal of the excavated material, has been issued with favourable outcome.
21/01/2015
The Project Change determination ((DVA-2015-0001796 of 21 January 2015) related to A12 Rosignano-Civitavecchia motorway. Branch Civitavecchia-Tarquinia Lot 6A. Non-substantial variations in the project approved, has been issued with favourable outcome.
21/01/2015
The EIA compliance determination (DVA-2015-0001734 of 21 January 2015) on the prescription 18 (V year of environmental monitoring - final report) of the EIA decision no. 10 of 10 January 2008 has been issued with favourable outcome.
21/01/2015
The EIA decision (D.M. 11 of 21 January 2015) related to the project Motorway A1 Milan-Naples: extension to third lane for the section Florence South - Incisa Valdarno - San Donato variant, has been issued with favourable outcome.
19/01/2015
The EIA compliance (Strategic works Law 443/2001) determination (DVA-2015-0001574 of 19 January 2015) on the prescriptions of the CIPE Decision n.57 of 3 August 2011 has been issued with favourable outcome.
14/01/2015
The EIA compliance determination (DVA-2015-0000965 of 14 January 2015) on the prescription 1.7 (first semester 2014) of the EIA decision no.1832 of 1 December 2009 has been issued with favourable outcome.
13/01/2015
The EIA compliance determination (DVA-2015-0000917 of 13 January 2015) on the prescriptions 2.1, 2.2, 2.3, 3.2, 3.5 of the EIA Screening determination no. 7281 of 23 March 2012 has been issued with partly favourable outcome.