Procedure Code (ID_VIP/ID_MATTM): |
3656 |
EIA-AA integrated Procedure : |
Sì |
Subject
: |
Progetto di variante in ottemperanza alla prescrizione n. 235 della Delibera CIPE 19/2015 - Localizzazione alternativa dei cantieri |
Date of application submission: |
11/07/2017 |
Publication date of the notice in newspapers: |
10/07/2017 |
Deadline of submission of Public Comments: |
09/09/2017 |
Technical assessment starting date: |
19/07/2017 |
Date of request for integrations: |
26/09/2017 |
Data ripubblicazione avviso sul sito web e avvio consultazione pubblica: |
27/10/2017 |
Deadline of submission of Public Comments on the republished project: |
26/11/2017 |
Republication subject
: |
Documentazione integrativa |
Date of integrations related to the republished project receipt: |
20/12/2017 |
Second Republication date of the notice: |
21/12/2017 |
Deadline of submission of Public Comments - Second republication: |
20/01/2018 |
Second republication subject
: |
Documentazione integrativa |
Date of the Opinion of the National Technical Commission : |
16/02/2018 |
National Technical Commission Opinion number: |
2647 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
22/02/2018 |
Notes: |
Con nota del 30/10/2017 (prot. DVA-2017-25104) è stata concessa una proroga di 60 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225903 - cress-5@minambiente.it |
Stage of the Procedure: |
Concluded |