Unsubstantial project changes (Strategic works Law 443/2001) |
|
10125 |
20/07/2023 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10125 |
Subject
: |
Progetto esecutivo Variazione delle geometrie di tracciato delle rampe per la realizzazione del nuovo autoporto, quale risoluzione di interferenza, nei Comuni di San Didero e Bruzolo |
Date of application submission: |
20/07/2023 |
Technical assessment starting date: |
09/08/2023 |
Date of the EIA Decree: |
22/09/2023 |
EIA Decree number: |
MASE_VA_DEC_2023-0000431 |
EIA Decree outcome: |
Positivo |
Communication date of the outcome to the developer: |
25/09/2023 |
Protocol of outcome communication to the developer: |
MASE_2023-0151188 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
7987 |
02/02/2022 |
Pending the start of the enivronmental monitoring
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
7987 |
Subject
: |
Progetto Esecutivo di cantierizzazione Fase 1 (Comuni di Chiomonte, Giaglione, Salbertrand, Susa e Area tecnica di Torrazza Piemonte) Lotto Costruttivo n. 1 e Piano di Gestione delle Terre della tratta italiana della Sezione Transfrontaliera |
Date of application submission: |
02/02/2022 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
05/08/2022 |
National Technical Commission Opinion number - Stage 1: |
538 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo con prescrizioni/raccomandazioni |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
28/09/2022 |
Determination number - Stage 1 : |
MiTE_VA_DEC_2022-0000248 |
Determination outcome - Stage 1: |
Positivo con prescrizioni/raccomandazioni |
Notification date: |
03/10/2022 |
Notification Reference number: |
MiTE-2022-0120349 |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Pending the start of the enivronmental monitoring
|
EIA Follow-up (Strategic works Law 443/2001) |
|
5712 |
07/12/2020 |
Ongoing environmental monitoring |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5712 |
Subject
: |
Nuova linea ferroviaria Torino-Lione - sezione internazionale - parte comune italo-francese. Sezione transfrontaliera. Parte in territorio italiano. Progetto esecutivo dello Spazio Visitatori provvisorio nel cantiere de La Maddalena (Comune di Chiomonte) - Lotto Costruttivo 1 - Cantiere Operativo CO04 |
Date of application submission: |
07/12/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
06/04/2021 |
National Technical Commission Opinion number - Stage 1: |
226 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
03/05/2021 |
Determination number - Stage 1 : |
DEC_2021-0000129 |
Determination outcome - Stage 1: |
Positivo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Ongoing environmental monitoring |
EIA Follow-up (Strategic works Law 443/2001) |
|
5029 |
09/12/2019 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5029 |
Subject
: |
Nuova linea ferroviaria Torino - Lione - sezione internazionale - parte comune italo-francese. Sezione transfrontaliera . Parte in territorio italiano. Opere di compensazione forestale , nei comuni di Giaglione, Chiomonte e Salbertrand, quale attività anticipatoria propedeutica all'avvio della cantierizzazione dei cantieri operativi nn.121, 131, 135 e 136 ed alla raccomandazione n.6 delle Delibere CIPE nn.30/2018 e 39/2018 ed esiti dei tavoli tecnici regionali e relativi protocolli di monitoraggio flora e fauna selvatica |
Date of application submission: |
09/12/2019 |
Date of notification to the developer of the procedure outcomes: |
06/11/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
12/10/2020 |
National Technical Commission Opinion number - Stage 1: |
PRR58 |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
30/10/2020 |
Determination number - Stage 1 : |
DEC388 |
Determination outcome - Stage 1: |
Positivo |
Notification Reference number: |
MATTM-2020-0090681 |
Outcome: |
Positivo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Follow-up (Strategic works Law 443/2001) |
|
4464 |
21/01/2019 |
Ongoing environmental monitoring |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4464 |
Subject
: |
Rilocalizzazione dell'autoporto nei Comuni di San Didero e Bruzolo (I lotto costruttivo). Progetto esecutivo. |
Date of application submission: |
21/01/2019 |
Date of notification to the developer of the procedure outcomes: |
14/02/2020 |
National Technical Commission Opinion number - Stage 1: |
3225 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
14/02/2020 |
Determination number - Stage 1 : |
MATTM_DEC_2020-0000010 |
Determination outcome - Stage 1: |
Positivo |
National Technical Commission Opinion number - Stage 2: |
721 |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
05/05/2023 |
Determination number - Stage 2 : |
MASE_VA_DEC_2023-0000227 |
Determination outcome - Stage 2: |
conclusa |
Notification date: |
15/05/2023 |
Notification Reference number: |
MASE_2023-0077898 |
Outcome: |
Positivo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Ongoing environmental monitoring |
EIA Follow-up (Strategic works Law 443/2001) |
|
4193 |
31/07/2018 |
Pending the start of the enivronmental monitoring
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4193 |
Subject
: |
Progetto Esecutivo Svincolo di Chiomonte in fase di cantiere, nei comuni di Chiomonte e Giaglione. I Lotto costruttivo |
Date of application submission: |
31/07/2018 |
Date of notification to the developer of the procedure outcomes: |
22/12/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
18/10/2019 |
National Technical Commission Opinion number - Stage 1: |
PRR 3152 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
21/11/2019 |
Determination number - Stage 1 : |
DEC 369 |
Determination outcome - Stage 1: |
Positivo |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
20/11/2020 |
National Technical Commission Opinion number - Stage 2: |
PRR-94 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
21/12/2020 |
Determination number - Stage 2 : |
DEC-523 |
Determination outcome - Stage 2: |
Positivo |
Notification Reference number: |
MATTM-2020-0107810 |
Outcome: |
Positivo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Pending the start of the enivronmental monitoring
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
3656 |
11/07/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3656 |
EIA-AA integrated Procedure : |
Sì |
Subject
: |
Progetto di variante in ottemperanza alla prescrizione n. 235 della Delibera CIPE 19/2015 - Localizzazione alternativa dei cantieri |
Date of application submission: |
11/07/2017 |
Publication date of the notice in newspapers: |
10/07/2017 |
Deadline of submission of Public Comments: |
09/09/2017 |
Technical assessment starting date: |
19/07/2017 |
Date of request for integrations: |
26/09/2017 |
Data comunicazione avvio nuova consultazione pubblica: |
27/10/2017 |
Deadline of submission of Public Comments on the republished project: |
26/11/2017 |
Republication subject
: |
Documentazione integrativa |
Date of integrations related to the republished project receipt: |
20/12/2017 |
Second Republication date: |
21/12/2017 |
Deadline of submission of Public Comments - Second republication: |
20/01/2018 |
Second republication subject
: |
Documentazione integrativa |
Date of the Opinion of the National Technical Commission : |
16/02/2018 |
National Technical Commission Opinion number: |
2647 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
22/02/2018 |
Notes: |
Con nota del 30/10/2017 (prot. DVA-2017-25104) è stata concessa una proroga di 60 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
2312 |
19/04/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2312 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
19/04/2013 |
Publication date of the notice in newspapers: |
15/04/2013 |
Deadline of submission of Public Comments: |
18/06/2013 |
Technical assessment starting date: |
23/04/2013 |
Date of integrations receipt: |
18/12/2013 |
Date of the Opinion of the National Technical Commission on usage Plan: |
12/12/2014 |
Opinion number of the National Technical Commission on usage Plan: |
1674 |
Usage Plan Determination date: |
19/01/2015 |
Determination number on usage Plan: |
DVA-2015-0001574 |
Date of the Opinion of the National Technical Commission : |
12/12/2014 |
National Technical Commission Opinion number: |
1674 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
22/12/2014 |
Date of CIPE Deliberation: |
20/02/2015 |
CIPE Deliberation number : |
19 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
06/08/2015 |
Italian Republic Official Journal number : |
181 |
Notes: |
Tenuto conto degli avvisi al pubblico da parte del Proponente e limitatamente al caso di specie, il periodo di osservazione del pubblico è esteso a 60gg. |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance (Strategic works Law 443/2001) |
|
2313 |
17/04/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2313 |
Subject
: |
Progetto Definitivo di prima fase. Prescrizioni della Delibera CIPE n.57 del 03/08/2011 |
Date of application submission: |
17/04/2013 |
Technical assessment starting date: |
02/05/2013 |
Date of notification to the developer of the procedure outcomes: |
16/12/2019 |
Date of the Opinion of the National Technical Commission : |
12/12/2014 |
National Technical Commission Opinion number: |
1674 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
19/01/2015 |
Determination number: |
DVA-2015-0001574 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
DVA/2019/32707 |
Amending Determination date: |
12/12/2019 |
Amending Determination number: |
DEC 429 |
Notes: |
Con il provvedimento direttoriale del 28/08/2013 (prot.DVA-2013-0019709) è stata determinata l'ottemperanza della prescrizione n.196 della Delibera CIPE n.57 del 03/08/2011 relativa alla ristrutturazione della parte di Caserma Henry da destinare a punto informativo a Susa. |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |