Procedure Code (ID_VIP/ID_MATTM): |
7636 |
Subject
: |
Progetto di un impianto agrovoltaico denominato "Cluster Lopez", delle opere ed infrastrutture connesse, sito nei comuni di Brindisi (BR) e Mesagne (BR), con potenza nominale pari a 30 MW e potenza di picco pari a 34,63992 MW. |
Date of application submission: |
18/11/2021 |
Data avvio consultazione pubblica: |
17/03/2022 |
Deadline of submission of Public Comments: |
15/06/2022 |
Date of request for documents perfection : |
24/02/2022 |
Date of perfection proceedings documents receipt: |
02/03/2022 |
Date of request for integrations: |
20/06/2022 |
Date of integrations receipt: |
07/07/2022 |
Data comunicazione avvio nuova consultazione pubblica: |
25/07/2022 |
Deadline of submission of Public Comments on the republished project: |
09/08/2022 |
Second Republication date: |
26/08/2022 |
Deadline of submission of Public Comments - Second republication: |
10/09/2022 |
Date of the Opinion of the CTPNRR-PNIEC: |
06/10/2022 |
CTPNRR-PNIEC Opinion number: |
CTVA_2022-0007571 |
CTPNRR-PNIEC Opinion outcome: |
Positivo con prescrizioni/raccomandazioni |
Ministry of Cultural Heritage and Tourism Opinion date: |
06/12/2022 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
MiTE_2022-0153307 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Negativo |
Date of the EIA Decree: |
01/02/2024 |
EIA Decree number: |
MASE_2024-0018905 |
EIA Decree outcome: |
Positivo con prescrizioni/raccomandazioni |
Notification date: |
09/02/2024 |
Notification Reference number: |
MASE_2024-0025453 |
Notes: |
Al procedimento è applicato il differimento di 60 gg per effetto dell'art.51, c.9 del DL 50/2022 |
Responsible of the procedure: |
Silvia Terzoli - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |