Unsubstantial project changes (Strategic works Law 443/2001) |
10499 |
25/10/2023 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
10499 |
Subject
: |
Asse ferroviario Napoli - Bari. Variante linea ferroviaria Cancello-Napoli. Variante al Piano di utilizzo ai sensi dell'art. 8, del D.M. 161/2012 |
Date of application submission: |
25/10/2023 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Unsubstantial project changes (Strategic works Law 443/2001) |
6063 |
28/04/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
6063 |
Subject
: |
Asse Ferroviario Napoli-Bari - Itinerario Napoli-Bari, 1° tratta: Variante alla linea Napoli-Cancello - Stralcio delle uscite STI- Eliminazione di due torrini |
Date of application submission: |
28/04/2021 |
Date of notification to the developer of the procedure outcomes: |
16/07/2021 |
Date of the Opinion of the National Technical Commission : |
25/06/2021 |
National Technical Commission Opinion number: |
PRR118 |
National Technical Commission Opinion outcome: |
Positivo |
Date of the EIA Decree: |
14/07/2021 |
EIA Decree number: |
DEC236 |
EIA Decree outcome: |
Positivo |
Notification date: |
16/07/2021 |
Notification Reference number: |
MATTM-2021-0077882 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
5843 |
15/02/2021 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5843 |
Date of application submission: |
15/02/2021 |
Stage of the Procedure: |
Approved with/without prescriptions |
Unsubstantial project changes (Strategic works Law 443/2001) |
5747 |
28/12/2020 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5747 |
Subject
: |
Legge n. 164/2014 e s.m.i. Asse ferroviario Napoli-Bari. I tratta: Variante alla linea Napoli - Cancello |
Date of application submission: |
28/12/2020 |
Date of notification to the developer of the procedure outcomes: |
04/05/2021 |
Date of the Opinion of the National Technical Commission : |
06/04/2021 |
National Technical Commission Opinion number: |
84 |
National Technical Commission Opinion outcome: |
Positivo |
Date of the EIA Decree: |
30/04/2021 |
EIA Decree number: |
DEC_2021-0000127 |
EIA Decree outcome: |
Positivo |
Notification Reference number: |
MATTM-2021-0046768 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
4360 |
16/11/2018 |
Pending the start of the enivronmental monitoring
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4360 |
Subject
: |
Art. 1 del D.L. 12 settembre 2014 n. 133 |
Date of application submission: |
16/11/2018 |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
29/05/2019 |
Determination number - Stage 1 : |
DVA_DEC_2019-0000190 |
Determination outcome - Stage 1: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Pending the start of the enivronmental monitoring
|
Unsubstantial project changes (Strategic works Law 443/2001) |
4188 |
24/07/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4188 |
Subject
: |
Progetto Esecutivo delle prescrizioni nn. 14 - 15 - 18 di cui all' Allegato 1 della delibera del Commissario n. 22 del 19 maggio 2016. |
Date of application submission: |
24/07/2018 |
Technical assessment starting date: |
08/08/2018 |
Date of notification to the developer of the procedure outcomes: |
26/11/2018 |
Date of the Opinion of the National Technical Commission : |
09/11/2018 |
National Technical Commission Opinion number: |
2868 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-DEC-2018-0000433 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Unsubstantial project changes (Strategic works Law 443/2001) |
4148 |
03/07/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4148 |
Subject
: |
Progetto Esecutivo delle prescrizioni nn. 8-9-11-16-17-18-19-22-23-26-28 di cui all'Allegato 1 della Ordinanza del Commissario n. 21 del 16 maggio 2016 |
Date of application submission: |
03/07/2018 |
Technical assessment starting date: |
09/07/2018 |
Date of notification to the developer of the procedure outcomes: |
03/10/2018 |
Date of the Opinion of the National Technical Commission : |
14/09/2018 |
National Technical Commission Opinion number: |
2819 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-DEC-2018-0000377 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Unsubstantial project changes (Strategic works Law 443/2001) |
3996 |
27/03/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3996 |
Subject
: |
Opera anticipata "Viabilità Gaudello" in Comune di Acerra - Variante progettuale "Strada poderale dei Cani" |
Date of application submission: |
27/03/2018 |
Technical assessment starting date: |
06/04/2018 |
Date of notification to the developer of the procedure outcomes: |
03/07/2018 |
Date of the Opinion of the National Technical Commission : |
22/06/2018 |
National Technical Commission Opinion number: |
2774 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-DEC-2018-0000292 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
3165 |
29/10/2015 |
Pending the start of the enivronmental monitoring
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3165 |
Subject
: |
Progetto esecutivo viabilità Gaudello |
Date of application submission: |
29/10/2015 |
Date of notification to the developer of the procedure outcomes: |
24/07/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
15/01/2016 |
National Technical Commission Opinion number - Stage 1: |
1967 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo con prescrizioni |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
27/01/2016 |
Determination number - Stage 1 : |
DVA-DEC-2016-0000018 |
Determination outcome - Stage 1: |
Positivo con prescrizioni |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
15/05/2020 |
National Technical Commission Opinion number - Stage 2: |
3419 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo con prescrizioni |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
10/07/2020 |
Determination number - Stage 2 : |
209 |
Determination outcome - Stage 2: |
Positivo con prescrizioni |
Notification Reference number: |
57890 |
Outcome: |
Positivo con prescrizioni |
Notes: |
Determinazione direttoriale - Fase 2 (Monitoraggio ambientale Ante Operam e rispetto prescrizioni) del 21/04/2017, prot. DVA-DEC-2017-0000112 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Pending the start of the enivronmental monitoring
|
EIA Compliance (Strategic works Law 443/2001) |
3147 |
09/10/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3147 |
Date of application submission: |
09/10/2015 |
Technical assessment starting date: |
13/10/2015 |
Date of the Opinion of the National Technical Commission : |
04/03/2016 |
National Technical Commission Opinion number: |
2014 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
15/03/2016 |
Determination number: |
DVA-DEC-2016-0000084 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance (Strategic works Law 443/2001) |
2977 |
17/03/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2977 |
Subject
: |
Progetto definitivo viabilità Gaudello. Prescrizioni Delibera CIPE n.2 del 18/02/2013 |
Date of application submission: |
17/03/2015 |
Technical assessment starting date: |
19/03/2015 |
Date of the Opinion of the National Technical Commission : |
29/05/2015 |
National Technical Commission Opinion number: |
1793 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
05/06/2015 |
Determination number: |
DVADEC-2015-0000188 |
Determination outcome: |
Parzialmente ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
192 |
17/08/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
192 |
Date of application submission: |
17/08/2009 |
Publication date of the notice in newspapers: |
11/08/2009 |
Deadline of submission of Public Comments: |
16/10/2009 |
Technical assessment starting date: |
23/10/2009 |
Date of request for integrations: |
10/12/2009 |
Date of procedure suspension: |
26/02/2010 |
Date of the Opinion of the National Technical Commission : |
25/03/2010 |
National Technical Commission Opinion number: |
452 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
05/07/2010 |
Date of CIPE Deliberation: |
18/02/2013 |
CIPE Deliberation number : |
2 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
27/07/2013 |
Italian Republic Official Journal number : |
175 |
Stage of the Procedure: |
Concluded |