EIA Follow-up (Strategic works Law 443/2001) |
4468 |
21/01/2019 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4468 |
Subject
: |
Raddoppio tratta Cencello-Benevento. 1° lotto funzionale Cancello-Dugenta/Frasso Telesino e Variante alla linea storica Roma-Napoli via Cassino nel Comune di Maddaloni. Art. 1 del D.L. 12 settembre 2014, n. 133. |
Date of application submission: |
21/01/2019 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
06/09/2019 |
National Technical Commission Opinion number - Stage 1: |
PAR 318 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
07/10/2019 |
Determination number - Stage 1 : |
DEC 309 |
Determination outcome - Stage 1: |
Positivo |
Notification Reference number: |
DVA/2019/26066 |
Outcome: |
11/10/2019 |
Notes: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Unsubstantial project changes (Strategic works Law 443/2001) |
4384 |
10/12/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4384 |
Subject
: |
Legge n. 164/2014 "Sblocca Italia" - Progetto esecutivo di cui alle prescrizioni nn. 16 e 17 dell'Allegato I all'Ordinanza del Commissario n.22/2016 |
Date of application submission: |
10/12/2018 |
Technical assessment starting date: |
20/12/2018 |
Date of notification to the developer of the procedure outcomes: |
06/05/2019 |
Date of the Opinion of the National Technical Commission : |
15/03/2019 |
National Technical Commission Opinion number: |
2975 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-2019-0011289 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
3384 |
28/06/2016 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3384 |
Subject
: |
"Itinerario Napoli - Bari" - Raddoppio tratta Cancello - Benevento. I lotto funzionale Cancello - Frasso Telesino e Variante alla linea Roma - Napoli via Cassino nel Comune di Maddaloni. - Progetto definitivo "Interconnessioni Nord sulla Linea Storica Roma -Napoli via Cassino". Progetto "Sblocca Italia", ex L. 164/2014. Aggiornamento ai sensi dell'art. 8, DM 161/2012 |
Date of application submission: |
28/06/2016 |
Date of the Opinion of the National Technical Commission on usage Plan: |
05/03/2021 |
Opinion number of the National Technical Commission on usage Plan: |
199 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato |
Usage Plan Determination date: |
24/03/2021 |
Determination number on usage Plan: |
MATTM_DEC_2021-0000095 |
Usage Plan Determination outcome: |
Approvato |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Approved with/without prescriptions |
Environmental Impact Assessment (Strategic works Law 443/2001) |
3383 |
28/06/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3383 |
Subject
: |
Interconnessioni Nord sulla Linea Storica Roma - Napoli via Cassino |
Date of application submission: |
28/06/2016 |
Publication date of the notice in newspapers: |
23/06/2016 |
Deadline of submission of Public Comments: |
28/07/2016 |
Technical assessment starting date: |
05/07/2016 |
Date of the Opinion of the National Technical Commission on usage Plan: |
11/11/2016 |
Opinion number of the National Technical Commission on usage Plan: |
2221 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato con prescrizioni |
Usage Plan Determination date: |
24/11/2016 |
Determination number on usage Plan: |
DVA-DEC-2016-0000406 |
Usage Plan Determination outcome: |
Approvato con prescrizioni |
Date of the Opinion of the National Technical Commission : |
24/11/2016 |
National Technical Commission Opinion number: |
2231 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
23/12/2016 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
3170 |
04/11/2015 |
Approved with/without prescriptions |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3170 |
Subject
: |
Piano di Utilizzo ai sensi del D.M.161/2012 - Progetto definitivo "Itinerario Napoli - Bari" Raddoppio Tratta Cancello - Benevento. I lotto funzionale Cancello - Frasso Telesino e Variante alla linea Roma - Napoli via Cassino nei Comune di Maddaloni - Aggiornamento ai sensi dell'art. 8, DM 161/2012 |
Date of application submission: |
04/11/2015 |
Date of the Opinion of the National Technical Commission on usage Plan: |
05/03/2021 |
Opinion number of the National Technical Commission on usage Plan: |
199 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato |
Usage Plan Determination date: |
24/03/2021 |
Determination number on usage Plan: |
MATTM_DEC_2021-0000095 |
Usage Plan Determination outcome: |
Approvato |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Approved with/without prescriptions |
EIA Compliance (Strategic works Law 443/2001) |
3169 |
04/11/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3169 |
Subject
: |
Approvazione Progetto Definitivo |
Date of application submission: |
04/11/2015 |
Technical assessment starting date: |
10/11/2015 |
Date of integrations receipt: |
22/12/2015 |
Date of integrations second receipt: |
11/03/2016 |
Date of the Opinion of the National Technical Commission on usage Plan: |
18/03/2016 |
Opinion number of the National Technical Commission on usage Plan: |
2024 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato con prescrizioni |
Usage Plan Determination date: |
24/03/2016 |
Determination number on usage Plan: |
DVA-DEC-2016-0000103 |
Usage Plan Determination outcome: |
Approvato con prescrizioni |
Date of the Opinion of the National Technical Commission : |
18/03/2016 |
National Technical Commission Opinion number: |
2025 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Determination date: |
24/03/2016 |
Determination number: |
DVA-DEC-2016-0000102 |
Determination outcome: |
Positivo con prescrizioni |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
3164 |
29/10/2015 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3164 |
Subject
: |
Progetto esecutivo della viabilità di soppressione PL al Km 143+833 - Via Calabroni |
Date of application submission: |
29/10/2015 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
19/02/2016 |
National Technical Commission Opinion number - Stage 1: |
1994 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
25/02/2016 |
Determination number - Stage 1 : |
DVA-DEC-2016-0000058 |
Determination outcome - Stage 1: |
Positivo |
Notes: |
Determinazione direttoriale - Fase 2 (Monitoraggio ambientale Ante Operam) del 18/09/2017, prot. DVA-DEC-2017-0000260 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
EIA Compliance (Strategic works Law 443/2001) |
2997 |
08/04/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2997 |
Subject
: |
Progetto definitivo della viabilità di soppressione del passaggio a livello al km 143+833 - Via Calabroni |
Date of application submission: |
08/04/2015 |
Technical assessment starting date: |
16/04/2015 |
Date of the Opinion of the National Technical Commission : |
29/05/2015 |
National Technical Commission Opinion number: |
1798 |
National Technical Commission Opinion outcome: |
Parzialmente Ottemperata |
Determination date: |
05/06/2015 |
Determination number: |
DVA-DEC-2015-0000189 |
Determination outcome: |
Parzialmente Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
191 |
17/08/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
191 |
Date of application submission: |
17/08/2009 |
Publication date of the notice in newspapers: |
11/08/2009 |
Deadline of submission of Public Comments: |
10/10/2009 |
Date of the Opinion of the National Technical Commission : |
25/03/2010 |
National Technical Commission Opinion number: |
434 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
16/07/2010 |
Stage of the Procedure: |
Concluded |