Subject
: |
Nuova linea ferroviaria Torino-Lione - sezione internazionale - parte comune italo-francese. Sezione transfrontaliera. Parte territorio italiano. Progetto esecutivo nicchie di interscambio all'interno del cunicolo esplorativo de La Maddalena (Lotto Costruttivo 1). Aggiornamento del layout di cantiere |
Date of application submission: |
10/03/2022 |
Technical assessment starting date: |
18/03/2022 |
Date of the Opinion of the National Technical Commission : |
20/05/2022 |
National Technical Commission Opinion number: |
260 |
National Technical Commission Opinion outcome: |
Positivo |
Date of the EIA Decree: |
17/06/2022 |
EIA Decree number: |
MiTE_VA_DEC_2022-0000101 |
EIA Decree outcome: |
Positivo |
Notification date: |
21/06/2022 |
Notification Reference number: |
MiTE-2022-0077382 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
5340 |
15/06/2020 |
Ongoing environmental monitoring |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5340 |
Subject
: |
Nuova linea ferroviaria Torino-Lione - sezione internazionale - parte comune italo-francese. Sezione transfrontaliera. Parte territorio italiano. Progetto esecutivo relativo ai lavori di realizzazione delle nicchie di interscambio all'interno del cunicolo esplorativo de La Maddalena (Lotto Costruttivo 1) |
Date of application submission: |
15/06/2020 |
Date of notification to the developer of the procedure outcomes: |
18/12/2020 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
20/11/2020 |
National Technical Commission Opinion number - Stage 1: |
PRR-96 |
National Technical Commission Opinion outcome - Stage 1: |
Positivo |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
17/12/2020 |
Determination number - Stage 1 : |
DEC-501 |
Determination outcome - Stage 1: |
Positivo |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
28/05/2021 |
National Technical Commission Opinion number - Stage 2: |
258 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
16/06/2021 |
Determination number - Stage 2 : |
DEC_2021-0000195 |
Determination outcome - Stage 2: |
Positivo |
Notification Reference number: |
MATTM-2020-0106494 |
Outcome: |
Positivo |
Responsible of the procedure: |
Barbara Mulattieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Ongoing environmental monitoring |