Unsubstantial project changes (Strategic works Law 443/2001) |
|
2684 |
12/03/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2684 |
Subject
: |
Aree di deposito definitivo delle terre e rocce da scavo |
Date of application submission: |
12/03/2014 |
Technical assessment starting date: |
17/03/2014 |
Date of notification to the developer of the procedure outcomes: |
04/09/2014 |
Date of the Opinion of the National Technical Commission : |
01/08/2014 |
National Technical Commission Opinion number: |
1594 |
National Technical Commission Opinion outcome: |
Positivo |
Notification Reference number: |
DVA-2014-0028200 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
Unsubstantial project changes (Strategic works Law 443/2001) |
|
2035 |
26/09/2012 |
Concluded |
Procedure details
|
|
Procedure Code (ID_VIP/ID_MATTM) |
2035 |
Subject
: |
Realizzazione della E90 tratto S.S. 106 da Ardore a Marina di Gioiosa Jonica (tratto Palizzi-Caulonia ex lotti 6,7,8) incluso lo svincolo di Marina di Gioiosa Jonica. Siti di deposito definitivo per le terre e rocce da scavo. |
Date of application submission: |
26/09/2012 |
Technical assessment starting date: |
10/10/2012 |
Date of notification to the developer of the procedure outcomes: |
01/03/2013 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
Unsubstantial project changes (Strategic works Law 443/2001) |
|
1570 |
15/09/2011 |
Concluded |
Procedure details
|
|
Procedure Code (ID_VIP/ID_MATTM) |
1570 |
Subject
: |
Variante Tecnica relativa al progetto denominato S.S. 106 Jonica - Lavori di realizzazione della E90 tratto S.S. 106 da Ardore a Marina di Gioiosa Jonica (tratto Palizzi-Caulonia ex lotti 6,7,8) compreso lo svincolo di Marina di Gioiosa Jonica |
Date of application submission: |
15/09/2011 |
Technical assessment starting date: |
27/09/2011 |
Date of notification to the developer of the procedure outcomes: |
09/01/2013 |
Date of the Opinion of the National Technical Commission : |
21/12/2012 |
National Technical Commission Opinion number: |
1146 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Notification Reference number: |
DVA-2013_0000574 |
Outcome: |
Positivo con prescrizioni |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
|
189 |
27/03/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
189 |
Subject
: |
Varianti e ottimizzazione al piano di cantierizzazione dell'opera |
Date of application submission: |
27/03/2009 |
Technical assessment starting date: |
13/11/2009 |
Date of the Opinion of the National Technical Commission : |
11/02/2010 |
National Technical Commission Opinion number: |
420 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
16/07/2010 |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
|
475 |
28/01/2009 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
475 |
Subject
: |
Lavori di ammodernamento in nuova sede della S.S. 106 Jonica - Megalotto 1 -Tratta Palizzi (km 50+000) - Caulonia (km 123+800). Ex lotti 6 - 7 - 8 da Ardore a Marina di Gioiosa Jonica compreso compreso lo svincolo di Marina Gioiosa Jonica |
Date of application submission: |
28/01/2009 |
Date of notification to the developer of the procedure outcomes: |
11/06/2019 |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
12/04/2019 |
National Technical Commission Opinion number - Stage 2: |
2997 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
10/06/2019 |
Determination number - Stage 2 : |
DVA_DEC_2019-0000202 |
Determination outcome - Stage 2: |
Positivo |
Notification Reference number: |
DVA_2019-0014869 |
Outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mase.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance (Strategic works Law 443/2001) |
|
765 |
13/01/2006 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
765 |
Date of application submission: |
13/01/2006 |
Technical assessment starting date: |
27/02/2006 |
Date of notification to the developer of the procedure outcomes: |
30/05/2007 |
Date of Special EIA Commission Opinion: |
25/05/2007 |
Special EIA Commission Opinion outcome: |
Ottemperato con condizioni |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
|
1330 |
24/10/2001 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1330 |
Date of application submission: |
24/10/2001 |
Date of the EIA Decree: |
14/01/2004 |
EIA Decree number: |
DSA-DEC-2004_0000001 |
EIA Decree outcome: |
Positivo con prescrizioni |
Stage of the Procedure: |
Concluded |